THE SENATE |
S.B. NO. |
66 |
THIRTY-THIRD LEGISLATURE, 2025 |
S.D. 2 |
|
STATE OF HAWAII |
H.D. 3 |
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO HOUSING.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
The legislature further finds that some of the largest obstacles for developers to construct more housing in the State are:
(1) A lack of areas with proper zoning to allow for the construction of residential dwellings;
(2) A lack of infrastructure to support newly developed residential dwellings; and
(3) Delays in the issuance of building permits for single‑family and multi-family projects.
The building permit processing times for single-family and multi-family projects vary tremendously across the United States. However, the counties in Hawaii seem to have some of the longest processing times for residential building permits. An April 2022 study prepared by the university of Hawaii economic research organization found that, on average, Hawaii homebuilders wait three times longer for permits than those in other states, which drives up costs significantly and creates uncertainty, serving as a disincentive to build new projects. Furthermore, the study found that compared to the most regulated markets in the country, Hawaii's permit delays are almost two times longer, meaning it can take from one year to one and a half years for a permit to be approved.
The legislature also finds that lengthy processing times to obtain a building permit raises the question: What information is necessary for counties when processing building permit applications? The basic responsibilities of the counties are to ensure compliance with various building codes and ensure adequate infrastructure capacity to support the proposed project or development. Although it is the counties' responsibility to monitor for compliance with various building codes, if the construction plans do not satisfy the code and are not corrected before construction, the designer, who is a licensed professional who stamped the plans, and the contractor are ultimately responsible. The counties are also not typically involved in litigation as the building permit process is ministerial, mainly to check for code compliance.
In other municipalities around the country, building plans are not scrutinized to the extent that they are in Hawaii counties. In Hawaii, the plan review is to ensure that the design meets all applicable codes. However, in other municipalities, the plans are used as a guide while code compliance verification is completed upon inspection of the project during construction. Inspectors who find that construction does not satisfy the code either have the correction made in the field or stop construction until proper corrective actions have been taken to ensure that new construction meets the code. Ultimately, the designer and contractor are responsible for ensuring new construction meets all applicable codes.
Accordingly, the purpose of this Act is to require permits to be issued within sixty days for certain single-family and multi-family housing projects if certain conditions are satisfied.
SECTION 2. Chapter 46, Hawaii Revised Statutes, is amended by adding a new section to be appropriately designated and to read as follows:
"§46- Single-family and multi-family housing
project permit applications; review time limit. (a)
For single-family and multi-family housing projects in each county, a
permit shall be issued within sixty days of filing of a complete application,
which shall include full and complete plans and a statement from the relevant
permitting agency that adequate infrastructure capacity is available to service
the project site. During the sixty-day
period after the permit application has been filed, the respective county shall
ensure that the project is in compliance with chapter 6E and all applicable
ordinances regarding land use, set‑back, height, and site development
requirements for the project site; provided that noncompliance with any state law
or county ordinance may delay the county's
issuance of the permit. If the county
determines that the application is not complete or if the county requires
additional information, corrections, or clarification regarding the permit
application, the county shall notify the applicant and specify the information
needed to meet the applicable permit requirements and the sixty-day review
period shall be paused until a complete application is made to the county. If an applicant does not accept all
corrections, changes, or recommendations made by the applicable permitting
agency to the plans submitted by the applicant, the sixty-day review period
shall be paused until revised full and complete plans are submitted to the
applicable permitting agency.
(b) Except as provided in subsection (c), a
permit submitted under this section shall be deemed approved if:
(1) The permit has not been approved by
the applicable permitting agency within sixty days of filing of a complete
application; or
(2) The applicant has submitted a full and complete plan and agrees to all corrections, changes, or recommendations to the plan made by the applicable permitting agency.
(c) A permit that has not been approved by the
applicable permitting agency within sixty days of filing a complete application
shall not be deemed approved if:
(1) The sixty-day permit review period
has been paused to allow the applicant to respond to any additional
information, corrections, or clarifications regarding the permit application
requested by the applicable permitting agency or to revise any plans in response
to any corrections, changes, or recommendations to the plans made by the
applicable permitting agency; or
(2) Approval of the permit has been
delayed due to noncompliance of the permit with applicable state law or county
ordinances.
(d) A county shall not consider an application
complete until:
(1) Either:
(A) Qualified
county professionals who meet state historic preservation division rules
governing professional qualifications for architecture, archaeology,
architectural history, or physical anthropology have made a reasonable and good‑faith
determination that the project does not have the potential to affect historic
properties, archaeological resources, or burial sites; or
(B) The
project has been submitted to the state historic preservation division of the
department of land and natural resources and the
chapter 6E process has been completed, including for those situations in which the
county professional described in subparagraph (A) determines that the project
may have the potential to affect historic properties, archaeological resources,
or burial sites; and
(2) The applicant
submits documentation evidencing that the proposed project
does not encroach on special flood hazard areas identified as "A" or
"V" zones on the Federal Emergency Management Agency's Flood
Insurance Rate Maps, or the applicable county official has reviewed the
proposed project for floodplain management
compliance and has issued a development permit for construction.
(e) Each county may adopt rules pursuant to
chapter 91 to effectuate the purposes of this section.
(f) Nothing in this section shall be construed to
allow any violation of federal, state, or county laws, rules, or ordinances.
(g) For the purposes of this section, "full and complete plans" means a plan submitted to a county that has been stamped by a duly licensed structural, civil, electrical, or mechanical engineer and architect certifying that all plans and specifications are in compliance with the applicable building codes for the respective county."
SECTION 3. New statutory material is underscored.
SECTION 4. This Act shall take effect on July 1, 3000, and shall be repealed on June 30, 2030.
Report Title:
Housing; Counties; Permits; Permitting Agencies; Review Time Limits; Code Compliance
Description:
Requires permits to be issued by applicable permitting agencies within sixty days of a complete application being filed for single-family and multi-family housing projects if certain conditions are satisfied. Automatically deems approved a permit that is either not otherwise approved by the applicable permitting agency within sixty days or for which the applicant has agreed to all corrections, changes, or recommendations to the plans and specifications made by the applicable permitting agency. Pauses the sixty day permit review period under certain circumstances. Sunsets 6/30/2030. Effective 7/1/3000. (HD3)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.