HOUSE OF REPRESENTATIVES |
H.B. NO. |
420 |
THIRTY-THIRD LEGISLATURE, 2025 |
H.D. 3 |
|
STATE OF HAWAII |
S.D. 2 |
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO REMEDIES.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. Section 657-8, Hawaii Revised Statutes, is amended to read as follows:
"§657-8
Limitation of action for damages based on construction to improve real
property. (a) No action, whether in contract, tort,
statute, or otherwise, to recover damages for any injury to property, real
or personal, or for bodily injury or wrongful death, arising out of any
deficiency or neglect in the planning, design, construction, supervision and
administering of construction, and observation of construction relating to an
improvement to real property shall be commenced [more than two years after
the cause of action has accrued, but in any event not] more than ten years
after the date of completion of the improvement.
(b) This section shall not be construed to extend
any shorter period of limitation under chapter 657, including the six-year
statute of limitations under section 657-1 or the two‑year statute of
limitations for damages to persons or property under section 657-7, as
applicable, subject to the ten‑year statute of repose under subsection
(a).
[(b)]
(c) This section shall not apply
to actions for damages against owners or other persons having an interest in
the real property or improvement based on their negligent conduct in the repair
or maintenance of the improvement or to actions for damages against surveyors
for their own errors in boundary surveys.
[The term "improvement" as used in this section shall have
the same meaning as in section 507-41 and the phrase "date of
completion" as used in this section shall mean the time when there has been
substantial completion of the improvement or the improvement has been
abandoned. The filing of an affidavit of
publication and notice of completion with the circuit court where the property
is situated in compliance with section 507-43(f) shall be prima facie evidence
of the date of completion.] An
improvement shall be deemed substantially complete upon the earliest of the
following:
(1) The issuance of a certificate of occupancy; or
(2) The filing of an affidavit of publication and notice of completion within the circuit court of the judicial circuit where the property is situated in compliance with section 507-43(f).
If the improvement consists of multiple buildings or improvements, each building or improvement shall be considered as a separate improvement for the purpose of determining the limitations period set forth in this section.
(d) This section shall not be construed to prevent, limit, or extend any shorter period of limitation applicable to sureties provided for in any contract or bond or any other statute, nor to extend or add to the liability of any surety beyond that for which the surety agreed to be liable by contract or bond.
[(c)]
(e) Nothing in this section shall
exclude or limit the liability provisions as set forth in the products
liability laws.
(f) For the purposes of this section:
"Date of completion" means the time when there has been substantial completion of the improvement or the improvement has been abandoned.
"Improvement"
has the same meaning as defined in section 507-41."
SECTION 2. Section 672E-3, Hawaii Revised Statutes, is amended to read as follows:
"[[]§672E-3[]]
Notice of claim of construction defect. (a) A
claimant, no later than ninety days before filing an action against a
contractor, shall serve the contractor with a written notice of claim. The notice of claim shall [describe the
claim in detail and include the results of any testing done.]:
(1) State that the
claimant asserts a claim against the contractor for a construction defect in
the design, construction, or remodeling, or any combination thereof, of a
dwelling or premises; and
(2) Describe the
claim in detail sufficient to determine the circumstances constituting the
alleged construction defect and damages resulting from the construction
defect. The description shall
specifically identify the alleged defect or problem; provided that a general
statement that a construction defect may exist shall be insufficient.
The notice of claim shall not
constitute a claim under any applicable insurance policy and shall not give
rise to a duty of any insurer to provide a defense under any applicable
insurance policy unless and until the process [set forth] described
in section 672E‑5 is completed.
Nothing in this chapter shall in any way interfere with or alter the
rights and obligations of the parties under any liability policy.
(b) If available to the claimant, the claimant
shall provide to the contractor, with the notice of claim, evidence that
depicts the nature and cause of the construction defect and the nature and extent
of the repairs necessary to repair the defect, including the following
information if obtained by the claimant:
photographs, videotapes, and any testing performed.
[(b)] (c) A contractor served with a written notice of
claim shall serve any other appropriate subcontractor with notice of the
claim. The contractor's notice shall
include the claimant's written notice of claim.
[(c)] (d) After serving the notice of claim, a claimant
shall give to the contractor reasonable prior notice and an opportunity to
observe if any testing is done."
SECTION 3. Section 672E-4, Hawaii Revised Statutes, is amended to read as follows:
"§672E-4 Rejection of claim; opportunity to repair
construction defect. (a)
The contractor rejects a claimant's claim of construction defects by:
(1) Serving
the claimant with a written rejection of the claim; or
(2) Failing
to respond pursuant to subsection (b)(1) or [(b)(2),] (2) to the
notice of claim within thirty days after service.
(b)
The contractor, within thirty days after service of the notice of claim,
shall serve the claimant and any other contractor that has received the notice
of claim with a written response to the alleged construction defect that:
(1) Offers
to settle without inspecting the construction defect by:
(A) Monetary
payment;
(B) Making
repairs; or
(C) Both
subparagraphs (A) and (B); or
(2) Proposes
to inspect the premises of the alleged construction defect that is the subject
of the claim.
(c)
Within thirty days following any proposal for inspection under
subsection (b)(2), the claimant shall [provide access to:] accept a
contractor's proposal to inspect. After
accepting the contractor's proposal to inspect, the claimant and contractor
shall agree on a time and date for the inspection, which shall occur within
thirty days of the claimant's acceptance of the contractor's proposal to
inspect, unless the claimant and contractor agree to a later date. The claimant shall provide reasonable access
to the dwelling or premises during normal working hours to:
(1) Inspect
the premises;
(2) Document
any alleged construction defects; and
(3) Perform
any testing required to evaluate the nature, extent, and cause of the asserted
construction defect, and the nature and extent of any repair or replacement
that may be necessary to remedy the asserted construction defect;
provided
that if the claimant is an association under chapter 514B, the claimant shall
have forty-five days to provide [such] access. If access to an individual condominium unit
is necessary, and the association is unable to obtain [such] access,
then the association shall have a reasonable time to provide access. If destructive testing is required, the
contractor shall give advance notice of tests and return the premises to its
pre-testing condition. If inspection or
testing reveals a condition that requires additional testing to fully and
completely evaluate the nature, cause, and extent of the construction defect,
the contractor shall provide notice to the claimant of the need for additional
testing. The claimant shall provide
additional access to the dwelling or premises. If a claim is asserted on behalf of owners of
multiple dwellings, or multiple owners of units within a multi-family complex,
the contractor shall be entitled to inspect each of the dwellings or units.
(d)
Inspections and testing performed pursuant to this section
shall be completed within nine months of the contractor's request to inspect,
unless the parties agree or the court orders otherwise.
[(d)] (e) Within fourteen days following the inspection
and testing, the contractor shall serve on the claimant a written:
(1) Offer to fully or partially remedy the
construction defect at no cost to the claimant.
[Such] The offer shall include a description of
construction necessary to remedy the construction defect and a timetable for
the completion of the additional construction;
(2) Offer to settle the claim by monetary payment;
(3) Offer for a combination of repairs and monetary payment; or
(4) Statement that the contractor will not proceed further to remedy the construction defect.
(f) Upon receipt of the offer made under
subsection (b)(1), (e)(1), (e)(2), or (e)(3), the claimant, within thirty or
forty-five days, whichever applies pursuant to section 672E‑5(a), may
accept the offer and authorize the contractor to proceed with any repairs
offered under subsection (b)(1), (e)(1), or (e)(3), or deny the offer.
(g) Any offer of settlement under this section shall reference this section, and shall state that a claimant's failure to respond with a written notice of acceptance or rejection within thirty or forty-five days, whichever applies pursuant to section 672E-5(a), shall mean that the offer is rejected. Failure to serve a written offer or statement under this section shall be deemed a statement that the contractor will not proceed further."
SECTION 4. Section 672E-6, Hawaii Revised Statutes, is amended to read as follows:
"[[]§672E-6[]] Offer of settlement. (a) Any time after the service of the
notice of claim, any party may serve an offer of settlement.
(b) If the offer is accepted, the parties shall be deemed to have resolved the claim in whole or in part pursuant to the offer.
(c) An offer not accepted within the time
period required under section 672E-5, or ten days after service for any
subsequent offers, shall be deemed withdrawn and evidence thereof [is]
shall not be admissible except to determine entitlement to
recovery of costs. If the judgment
or award obtained in a subsequent proceeding is not more favorable than the
offer, the offeree shall pay the costs incurred by the offeror after the making
of the offer. The fact that an offer is
made and not accepted does not preclude a subsequent offer."
SECTION 5. Section 672E-7, Hawaii Revised Statutes, is amended to read as follows:
"[[]§672E-7[]] Mediation.
(a) If
the parties are unable to resolve the claim pursuant to section 672E‑5 or
672E‑6, all parties shall attempt to resolve the dispute through
mediation, even if mediation is not otherwise ordered or mandated by contract
or by law[.]; provided that the parties shall not be required to
attempt to resolve the dispute through mediation more than once.
(b) Mediation shall be completed within twelve months of the filing of the notice of the claim, unless the parties agree or the court orders otherwise."
SECTION 6. Section 672E-8, Hawaii Revised Statutes, is amended to read as follows:
"[[]§672E-8[]] Statute of limitations on actions exception. If an applicable statute of limitation or
repose would preclude an action after the notice of claim has been served but
before the dispute is resolved under this chapter, the claimant may file an
action against the contractor but the action shall be immediately stayed
pending the contractor's opportunity to repair under section 672E-4, or
submission of the dispute to mediation under section 672E-7[.];
provided that no action shall be filed pursuant to this section more than six
months before the end of the applicable limitation or repose period. This section shall not be construed to revive
a statutory period of limitations on actions that have expired prior to the
date on which a claimant's written notice of claim is served. After the sending of the initial notice of
claim, a claimant and a contractor, by written mutual agreement, may alter the
procedure for the notice of claim under this section."
SECTION 7. This Act does not affect rights and duties that matured, penalties that were incurred, and proceedings that were begun before its effective date.
SECTION 8. Statutory material to be repealed is bracketed and stricken. New statutory material is underscored.
SECTION 9. This Act shall take effect on July 1, 3000.
Report Title:
Statute of Repose; Contractor Repair Act; Notice of Claim; Inspection; Repair; Rejection of Claims; Construction Defect; Mediation; Statute of Limitations
Description:
Clarifies the applicability of the statute of repose to apply to contract, tort, and statutory claims. Clarifies the required contents of a notice of claim of a construction defect served on a contractor. Clarifies the process and time frame by which a claimant may accept or reject a contractor's offer to settle and authorize repairs. Clarifies the mediation process for construction defect claims. Clarifies the statute of limitation or response for construction defect claims. Effective 7/1/3000. (SD2)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.