THE SENATE |
S.B. NO. |
66 |
THIRTY-THIRD LEGISLATURE, 2025 |
S.D. 2 |
|
STATE OF HAWAII |
H.D. 1 |
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO HOUSING.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
The legislature further finds that some of the largest obstacles for developers to construct more housing in the State are:
(1) A lack of areas with proper zoning to allow for the construction of residential dwellings;
(2) A lack of infrastructure to support newly developed residential dwellings; and
(3) Delays in the issuance of building permits for single‑family and multi-family projects.
The building permit processing times for single-family and multi-family projects vary tremendously across the United States. However, the counties in Hawaii seem to have some of the longest processing times for residential building permits. An April 2022 study prepared by the university of Hawaii economic research organization found that, on average, Hawaii homebuilders wait three times longer for permits than those in other states, which drives up costs significantly and creates uncertainty, serving as a disincentive to build new projects. Furthermore, the study found that compared to the most regulated markets in the country, Hawaii's permit delays are almost two times longer, meaning it can take from one year to one and a half years for a permit to be approved.
The legislature also finds that lengthy processing times to obtain a building permit raises the question: What information is necessary for counties when processing building permit applications? The basic responsibilities of the counties are to ensure compliance with various building codes and ensure adequate infrastructure capacity to support the proposed project or development. Although the counties are responsible to monitor for compliance with various building codes, if the construction plans do not satisfy the code and are not corrected before construction, the designer (a licensed professional who stamped the plans) and the contractor are ultimately responsible. A county is also not typically involved in litigation as the building permit process is ministerial, mainly to check for code compliance.
In other municipalities around the country, building plans are not scrutinized to the extent that they are in Hawaii counties. In Hawaii, the plan review is to ensure that the design meets all applicable codes. However, in other municipalities, the plans are used as a guide while code compliance verification is completed upon inspection of the project during construction. Inspectors who find that construction does not satisfy the code either have the correction made in the field or stop construction until proper corrective actions have been taken to ensure that new construction meets the code. Ultimately, the design professional and contractor are responsible to ensure new construction meets all applicable codes.
Accordingly, the purpose of this Act is to require permits to be issued within sixty days for certain single-family and multi-family projects if certain conditions are satisfied.
SECTION 2. Chapter 46, Hawaii Revised Statutes, is amended by adding a new section to be appropriately designated and to read as follows:
"§46- Single-family and multi-family permit
applications; review time limit. (a) For single-family and multi-family projects
in each county, a permit shall be issued within sixty days of a complete
application being filed containing plans and specifications that are in
compliance with all relevant codes and standards for the respective
county. The completed application shall
include a statement from the relevant permitting agency that adequate
infrastructure capacity is available to service the project site. During the sixty-day period after the permit
application has been submitted, the respective county shall ensure that the
project is in compliance with chapter 6E and applicable ordinances regarding
land use, set‑back, height, and site development requirements for the
project site; provided that noncompliance with any state or county regulations
may delay the county's issuance of the permit.
If a permit submitted under this section is not approved by the
applicable permitting agency within sixty days of a complete application being
filed, it shall be deemed approved; provided that approval has not been delayed
due to noncompliance of the permit with applicable state law or county
ordinances. Nothing in this section
shall be construed to allow any violation of federal, state, or county laws,
rules, or ordinances.
(b) A county shall not consider an application
complete until:
(1) Either:
(B) The project has been submitted to the state historic preservation division of the department of land and natural resources and the chapter 6E process has been completed; and
(2) The developer submits documentation
evidencing that the proposed development does not encroach in special flood
hazard areas identified as "A" or "V" zones on the Federal
Emergency Management Agency's Flood Insurance Rate Maps, or the applicable
county official has reviewed the proposed development for floodplain management
compliance and has issued a development permit for construction.
(c) Each county may adopt rules pursuant to chapter 91 to effectuate the purposes of this section."
SECTION 3. New statutory material is underscored.
SECTION 4. This Act shall take effect on April 23, 2057.
Report Title:
Housing; Counties; Permits; Permitting Agencies; Review Time Limits; Code Compliance
Description:
Requires permits to be issued by applicable permitting agencies within sixty days of a complete application being filed for certain single-family and multi-family projects if certain conditions are satisfied. Automatically deems approved a permit that is not otherwise approved by the applicable permitting agency within sixty days. Effective 4/23/2057. (HD1)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.