SECTION 1. Chapter 269, Hawaii Revised Statutes, is amended by adding a new section to be appropriately designated and to read as follows:
"§269- Electric
utility and gas utility capital improvements; review; rate base. (a) An electric utility or gas utility shall submit proposed capital expenditures for any single project
related to plant replacement, expansion, or modernization in excess of
$500,000 or ten per cent of the total plant in service, whichever is less, to
the public utilities commission for review at least sixty days before the
commencement of construction or commitment for expenditure, whichever is
earlier.
(b) If
the commission determines, after a hearing on the matter, that any portion of
the proposed project provides facilities that are unnecessary or are
unreasonably in excess of probable future requirements for electric utility or
gas utility purposes, then the electric utility or gas utility shall not
include that portion of the project in its rate base. If the electric utility or gas utility
subsequently convinces the commission that the property in question is
necessary or useful for public utility purposes, then the property may be
included in the rate base.
(c) If
the commission does not render a decision and order within ninety days of
filing by the electric utility or gas utility, the electric utility or gas
utility may include the capital expenditures for the proposed project in its
rate base without the determination required by this section."
SECTION 2. New statutory material is underscored.
SECTION 3. This Act shall take effect on June 30, 3000.
Report Title:
PUC; Electric Utility; Gas Utility; Capital Improvements; Rate Base
Description:
Requires electric
utilities and gas utilities to submit proposed capital expenditures for certain
projects to the PUC for review and determination whether the project may be
included in the utilities' rate base.
Requires the PUC to make a determination within ninety days. Effective 6/30/3000. (HD1)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.