SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $29,887,500 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the seventeenth senatorial district, as follows:
1. Waipahu elementary school, Oahu
A. Construction and equipment for air conditioning for classrooms.
Construction $130,000
Equipment $120,000
Total funding $250,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
2. Waipahu high school, Oahu
A. Construction for replacement of broken gym bleachers.
Construction $2,000,000
Total funding $2,000,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
3. Waipahu high school, Oahu
A. Construction for a multipurpose athletic court improvement project, including resurfacing the current courts, which have created a safety issue for students.
Construction $1,000,000
Total funding $1,000,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
4. Waipahu high school, Oahu
A. Design and construction for re-keying of all exterior locks on campus.
Design $93,750
Construction $343,750
Total funding $437,500
The sum appropriated for this capital improvement project shall be expended by the department of education.
5. Waipahu high school, Oahu
A. Construction for phase 2 of campus painting.
Construction $600,000
Total funding $600,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
6. Palisades elementary school, Oahu
A. Design and construction for an outdoor covered play-court.
Design $1,077,000
Construction $4,423,000
Total funding $5,500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
7. Honowai elementary school, Oahu
A. Design and construction for covered walkways connecting buildings to the cafeteria, ground and site improvements, equipment and appurtenances.
Design $50,000
Construction $1,450,000
Total funding $1,500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
8. Pearl City elementary school, Oahu
A. Plans, design, and construction to resurface a driveway.
Plans $100,000
Design $100,000
Construction $2,000,000
Total funding $2,200,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
9. Pearl City elementary school, Oahu
A. Plans, design, and construction for slope stablization.
Plans $250,000
Design $250,000
Construction $5,000,000
Total funding $5,500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
10. Pearl City elementary school, Oahu
A. Plans, design, and construction to replace water supply lines.
Plans $250,000
Design $250,000
Construction $5,000,000
Total funding $5,500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
11. Pearl City elementary school, Oahu
A. Plans, design, and construction to replace playground equipment.
Plans $100,000
Design $100,000
Construction $2,000,000
Total funding $2,200,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
12. August Ahrens elementary school, Oahu
A. Construction to continue the whole-school renovation.
Construction $1,300,000
Total funding $1,300,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
13. August Ahrens elementary school, Oahu
A. Construction for a new school-wide unified communication bell and public address system.
Construction $650,000
Total funding $650,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
14. August Ahrens elementary school, Oahu
A. Construction for a new cooling system for building "M", electrical upgrades, and related improvements.
Construction $1,250,000
Total funding $1,250,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
SECTION 2. The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriations unencumbered as of June 30, 2024, shall lapse as of that date.
SECTION 3. This Act shall take effect on July 1, 2022.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 17th Senatorial District; Appropriation
Description:
Appropriates funds for capital improvement projects in the 17th senatorial district.