     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $85,023,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the thirteenth representative district, as follows:

1.   Haiku elementary school, Maui

     Construction and equipment for fencing surrounding the perimeter of the campus and peace garden and new motion lights and gates to secure the upper campus, administrative building, and classrooms, including electrical upgrades.

     Construction                 $4,000,000

     Equipment                    $3,000,000

          Total funding                     $7,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Hana high and elementary school, Maui

     Plans and construction for an amphitheater.

     Plans                           $50,000

     Construction                 $2,000,000

          Total funding                     $2,050,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Hana high and elementary school, Maui

     Plans and construction for girls and boys locker rooms.

     Plans                           $50,000

     Construction                   $800,000

          Total funding                       $850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Hana high and elementary school, Maui

     Plans and construction for multi-purpose athletic field.

     Plans                          $300,000

     Construction                 $1,000,000

          Total funding                     $1,300,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Hana high and elementary school, Maui

     Plans for new master facility plan with administrative offices and a new building for Kula Kaiapuni o Hana.

     Plans                           $50,000

          Total funding                        $50,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Kaunakakai elementary school, Molokai

     Construction for a roof for outdoor stage.

     Construction                    $50,000

          Total funding                        $50,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Kilohana elementary school, Molokai

     Plans, design, construction, and equipment for clearing land area north of school property, outdoor learning and recreational space, and covered structure for emergency safety drills.

     Plans                          $150,000

     Design                       $1,200,000

     Construction                   $250,000

     Equipment                       $50,000

          Total funding                     $1,650,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Kualapuu school, Molokai

     Construction and equipment for solar panels.

     Construction                   $150,000

     Equipment                      $400,000

          Total funding                       $550,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Kualapuu school, Molokai

     Plans, design, and equipment for a new playground.

     Plans                           $10,000

     Design                          $10,000

     Equipment                      $165,000

          Total funding                       $185,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Maunaloa elementary school, Molokai

     Construction for a multi-purpose outdoor covered learning area.

     Construction                 $3,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Molokai high school, Molokai

     Construction for gym louvers replacement, gym lift repair, gym roof and vent repair, removal of vegetation from gutters, resurfacing gym floor, resurfacing outdoor play courts, replacing fence for outdoor play courts, and covering for outdoor play courts.

     Construction                 $3,026,000

          Total funding                     $3,026,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Molokai middle school, Molokai

     Construction for drop-off/pick-up area.

     Construction                 $5,000,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

13.  Hāna health center, Maui

     Plans, design, construction, and equipment for modern health care and support service facilities in the Hāna District.

     Plans                           $10,000

     Design                          $10,000

     Construction                 $1,200,000

     Equipment                       $10,000

          Total funding                     $1,230,000

     The sum appropriated for this capital improvement project shall be expended by the department of health.

14.  Kalaupapa settlement, Molokai

     Plans, design, and construction for various improvements.

     Plans                            $1,000

     Design                           $1,000

     Construction                 $1,480,000

          Total funding                     $1,482,000

     The sum appropriated for this capital improvement project shall be expended by the department of health.

15.  Lanai Kinaole

     Construction for adult day care facility building.

     Construction                 $1,010,000

          Total funding                     $1,010,000

     The sum appropriated for this capital improvement project shall be expended by the department of health.

16.  Hana highway, Maui

     Design and construction for drainage improvements.

     Design                          $80,000

     Construction                 $1,200,000

          Total funding                     $1,280,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

17.  Hana highway, Maui

     Design and construction for guardrails.

     Design                           $1,000

     Construction                 $3,999,000

          Total funding                     $4,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

18.  Hana highway, Maui

     Design and construction for improvements, Uakea road.

     Design                         $160,000

     Construction                 $3,055,000

          Total funding                     $3,215,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

19.  Hana highway, Maui

     Design for Kailua stream bridge.

     Design                         $600,000

          Total funding                       $600,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

20.  Hana highway, Maui

     Design for Makanali stream bridge.

     Design                         $615,000

          Total funding                       $615,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

21.  Hana highway, Maui

     Land and design for Kopiliula stream bridge.

     Land                           $235,000

     Design                         $870,000

          Total funding                     $1,105,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

22.  Hana highway, Maui

     Land and design for Mokulehua stream bridge.

     Land                           $200,000

     Design                         $800,000

          Total funding                     $1,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

23.  Hana highway, Maui

     Land and design for Puohokamoa stream bridge.

     Land                           $180,000

     Design                         $730,000

          Total funding                       $910,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

24.  Hana highway, Maui

     Land and design for Ulaino stream bridge.

     Land                           $195,000

     Design                         $755,000

          Total funding                       $950,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

25.  Hana highway, Maui

     Land, design, and construction for improvements, milepost 28.1.

     Land                            $50,000

     Design                         $105,000

     Construction                   $675,000

          Total funding                       $830,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

26.  Hana highway, Maui

     Plans for bridge preservation.

     Plans                        $1,280,000

          Total funding                     $1,280,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

27.  Hana highway, Maui

     Plans, design, and construction for emergency repairs and improvements.

     Plans                          $100,000

     Design                         $100,000

     Construction                $19,800,000

          Total funding                    $20,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

28.  Hana highway, Maui

     Plans, design, and construction for pedestrian safety mitigation, Pilialoha street.

     Plans                            $1,000

     Design                           $1,000

     Construction                   $248,000

          Total funding                       $250,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

29.  Hana highway, Maui

     Plans, design, and construction for rockfall mitigation.

     Plans                          $265,000

     Design                         $735,000

     Construction                $12,132,000

          Total funding                    $13,132,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

30.  Kamehameha V highway, Molokai

     Land, design, and construction for drainage improvements.

     Land                            $50,000

     Design                          $40,000

     Construction                   $900,000

          Total funding                       $990,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

31.  State highways, Molokai

     Design and construction for guardrail and shoulder improvements.

     Design                         $333,000

     Construction                 $6,100,000

          Total funding                     $6,433,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2022.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Thirteenth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirteenth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.