THE SENATE |
S.B. NO. |
2655 |
THIRTIETH LEGISLATURE, 2020 |
S.D. 1 |
|
STATE OF HAWAII |
H.D. 1 |
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO UTILITY TRANSMISSION LINES.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. Section 269-27.6, Hawaii Revised Statutes, is amended to read as follows:
"§269-27.6 Construction of high-voltage electric transmission lines; overhead or underground construction. (a) Notwithstanding any law to the contrary, and as provided in subsection (b), whenever a public utility applies to the public utilities commission for approval to place, construct, erect, or otherwise build a new 46 kilovolt or greater high-voltage electric transmission system, either above or below the surface of the ground, the public utilities commission shall determine whether the electric transmission system shall be placed, constructed, erected, or built above or below the surface of the ground; provided that in its determination, the public utilities commission shall consider:
(1) Whether a benefit exists that outweighs the costs of placing the electric transmission system underground;
(2) Whether there is a governmental public policy requiring the electric transmission system to be placed, constructed, erected, or built underground, and the governmental agency establishing the policy commits funds for the additional costs of undergrounding;
(3) Whether any governmental agency or other parties are willing to pay for the additional costs of undergrounding;
(4) The recommendation of the division of consumer advocacy of the department of commerce and consumer affairs, which shall be based on an evaluation of the factors set forth under this subsection; and
(5) Any other relevant factors.
(b) Notwithstanding the requirements in
subsection (a), a public utility shall not be required to seek approval from
the public utilities commission to place, construct, erect, or otherwise build
a high-voltage electric transmission system, if the electric transmission
system is to be built underground and meets the following requirements:
(1) The entire cost
due to building underground, rather than above ground, is paid by an entity as
a contribution in aid of construction; and
(2) Prior to
commencing construction, the public utility provides a report to the public
utilities commission, with a copy to the consumer advocate, describing in
detail the electric transmission system and verifying that additional costs of
building underground will be paid by an entity other than the public utility;
provided that the public utilities commission shall have sixty days to take
action on the report submitted pursuant to this paragraph, or it shall be
assumed that the public utility may proceed with the project.
[(b)] (c) In making the determination set forth in
subsection (a), for new 138 kilovolt or greater high-voltage transmission
systems, the public utilities commission shall evaluate and make specific
findings on all of the following factors:
(1) The amortized cost of construction over the respective usable life of an above-ground versus underground system;
(2) The amortized cost of repair over the respective usable life of an above-ground versus underground system;
(3) The risk of damage or destruction over the respective usable life of an above-ground versus an underground system;
(4) The relative safety and liability risks of an above-ground versus underground system;
(5) The electromagnetic field emission exposure from an above-ground versus underground system;
(6) The proximity and visibility of an above-ground system to:
(A) High density population areas;
(B) Conservation and other valuable natural resource and public recreation areas;
(C) Areas of special importance to the tourism industry; and
(D) Other industries
particularly dependent on
(7) The length of the system;
(8) The breadth and depth of public sentiment with respect to an above-ground versus underground system; and
(9) Any other factors that the public utilities commission deems relevant.
[(c)] (d) A public utility making an application to the
public utilities commission under this section shall clearly and fully state
and support its evaluation of each factor set forth in subsection [(b).]
(c)."
SECTION 2. Statutory material to be repealed is bracketed and stricken. New statutory material is underscored.
SECTION 3. This Act shall take effect on July 1, 2050.
Report Title:
Public Utilities Commission; High-voltage Electric Transmission Lines; Underground Construction
Description:
Exempts a public utility from seeking approval from the public utilities commission to place, construct, erect, or build a high-voltage electric transmission system under certain circumstances. Effective 7/1/2050. (HD1)
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.