     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $226,550,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2019-2020 for the purpose of capital improvement projects for the twentieth senatorial district, as follows:

1.   Barbers point elementary

     Design and construction for air conditioning for entire school.

     Design                         $500,000

     Construction                 $4,500,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   East Kapolei elementary school

     Construction for a new elementary school.

     Construction                $61,000,000

          Total funding                    $61,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   East Kapolei high school

     Design for a new high school.

     Design                       $8,000,000

          Total funding                     $8,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   East Kapolei middle school

     Design, construction, and equipment for a new school, phase 3.

     Design                         $100,000

     Construction                $44,900,000

     Equipment                      $500,000

          Total funding                    $45,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Kapolei middle school

     Design and construction for a shelter in place for library, buildings A, C, E, F, G, H, and I.

     Design                         $150,000

     Construction                 $1,600,000

          Total funding                     $1,750,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Kapolei middle school

     Design and construction for restrooms for portables.

     Design                         $100,000

     Construction                   $750,000

          Total funding                       $850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Kapolei high school

     Design and construction for a shelter in place for administration, buildings B, D, G, and H.

     Design                         $200,000

     Construction                 $1,300,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Kapolei high school

     Design and construction for restrooms for portables.

     Design                         $100,000

     Construction                   $750,000

          Total funding                       $850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Kapolei high school

     Design, construction, and equipment for a new classroom building.

     Design                       $2,000,000

     Construction                $33,800,000

     Equipment                      $200,000

          Total funding                    $36,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Makakilo elementary school

     Design and construction for air conditioning for the entire school.

     Design                         $500,000

     Construction                 $4,500,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Mauka Lani elementary school

     Design and construction for air conditioning for the entire school.

     Design                         $500,000

     Construction                 $5,000,000

          Total funding                     $5,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Waipahu intermediate school

     Design and construction for air conditioning for the entire school.

     Design                         $600,000

     Construction                 $5,900,000

          Total funding                     $6,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

13.  Waipahu intermediate school

     Design and construction for multi-purpose play courts.

     Design                         $300,000

     Construction                 $1,900,000

          Total funding                     $2,200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

14.  Waipahu intermediate school

     Design, construction, and equipment for a new classroom building.

     Design                       $4,000,000

     Construction                $30,700,000

     Equipment                      $300,000

          Total funding                    $35,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

15.  Fort Barrette road improvements

     Construction for Fort Barrette road improvements; vicinity of Roosevelt Avenue to vicinity of Farrington highway, Oahu.

     Construction                 $1,400,000

          Total funding                     $1,400,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

16.  Kalaeloa Enterprise street lighting project; Kalaeloa, Oahu

     Design and construction for Kalaeloa Enterprise street lighting project; Kalaeloa, Oahu.

     Design                         $400,000

     Construction                 $1,600,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii community development authority.

17.  Kalaeloa improvement district project; Kalaeloa, Oahu

     Plans and design for Kalaeloa improvement district project; Kalaeloa, Oahu.

     Plans                          $500,000

     Design                       $2,000,000

          Total funding                     $2,500,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii community development authority.

18.  Villages of Kapolei road infrastructure rehabilitation and dedication

     Design and construction for villages of Kapolei road infrastructure rehabilitation and dedication - phase 1, Oahu.

     Design                         $400,000

     Construction                 $3,600,000

          Total funding                     $4,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii housing finance and development corporation.

19.  University of Hawaii West Oahu

     Plans, design, construction, and equipment for renewing, improving, and modernizing University of Hawaii West Oahu.

     Plans                            $2,000

     Design                           $2,000

     Construction                 $1,994,000

     Equipment                        $2,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the University of Hawaii.

     SECTION 2.  The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriations are made; provided that all moneys from the appropriations unencumbered as of June 30, 2022, shall lapse as of that date.


     SECTION 3.  This Act shall take effect on July 1, 2019.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Twentieth Senatorial District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the twentieth senatorial district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.