THE SENATE |
S.B. NO. |
2998 |
TWENTY-NINTH LEGISLATURE, 2018 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of THE fourteenth SENATORIAL DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $78,128,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2018-2019 for the purpose of capital improvement projects for the fourteenth senatorial district, as follows:
1. Aiea elementary school
A. Buildings E and G air conditioning improvements; ground and site improvements; equipment and appurtenances.
Design $800,000
Construction $1,000,000
Equipment $200,000
Total funding $2,000,000
B. Campus covered walkways; ground and site improvements; equipment and appurtenances.
Design $100,000
Construction $900,000
Total funding $1,000,000
2. Aiea intermediate school
A. Building D courtyard improvements; ground and site improvements; equipment and appurtenances.
Design $500,000
Construction $2,000,000
Total funding $2,500,000
B. Covered play court improvements; ground and site improvements; equipment and appurtenances.
Design $575,000
Construction $2,300,000
Total funding $2,875,000
3. Dole middle school
A. Build an open air covered student enrichment/activity area between two buildings.
Plans $50,000
Design $250,000
Construction $3,500,000
Equipment $200,000
Total funding $4,000,000
4. Kalihi elementary school
A. Exterior painting of all school buildings.
Design $50,000
Construction $260,000
Total funding $310,000
B. Repair basketball poles and resurface volleyball/basketball court.
Design $50,000
Construction $250,000
Total funding $300,000
C. Regrade grass landing and playing field.
Design $30,000
Construction $170,000
Total funding $200,000
5. Kalihi Uka elementary school
A. Install air conditioning on ground floor of the new pre-school in building C.
Construction $7,000
Equipment $21,000
Total funding $28,000
6. Kalihi Waena elementary school
A. Build utility center with a basketball court equipped for meetings, bathrooms on bottom level, and cardio room, classroom, and equipment room on upper level, including covered walkway.
Plans $15,000
Design $50,000
Construction $800,000
Equipment $100,000
Total funding $965,000
7. Major General William R. Shafter elementary school
A. Hillside erosion, stabilization, and control; ground and site improvements; equipment and appurtenances.
Design $100,000
Construction $400,000
Total funding $500,000
8. Moanalua elementary school
A. Electrical upgrade and air conditioning improvements; ground and site improvements; equipment and appurtenances.
Design $100,000
Construction $400,000
Equipment $100,000
Total funding $600,000
B. Multi-purpose innovation center; ground and site improvements; equipment and appurtenances.
Design $320,000
Construction $2,880,000
Equipment $50,000
Total funding $3,250,000
9. Moanalua middle school
A. Student drop-off/pick-up area improvements; ground and site improvements; equipment and appurtenances.
Design $600,000
Construction $1,500,000
Total funding $2,100,000
10. Webling elementary school
A. Expansion of support facilities (administration and library); ground and site improvements; equipment and appurtenances.
Design $800,000
Construction $6,650,000
Equipment $50,000
Total funding $7,500,000
B. Campus covered walkways; ground and site improvements; equipment and appurtenances.
Design $100,000
Construction $900,000
Total funding $1,000,000
11. Wallace Rider Farrington high school
A. School redesign project phase II; redesign of the school gym, band, choral, orchestra, and PE facilities.
Construction $48,880,000
Equipment $120,000
Total funding $49,000,000
SECTION 2. The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriations are made; provided that all moneys from the appropriations that are unencumbered as of June 30, 2020, shall lapse as of that date.
SECTION 3. The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended by the department of education.
SECTION 4. This Act shall take effect on July 1, 2018.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; Fourteenth Senatorial District
Description:
Appropriates funds for capital improvement projects in the fourteenth senatorial district.
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.