     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $78,128,000 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2018-2019 for the purpose of capital improvement projects for the fourteenth senatorial district, as follows:

1.   Aiea elementary school

     A.   Buildings E and G air conditioning improvements; ground and site improvements; equipment and appurtenances.

          Design                         $800,000

          Construction                 $1,000,000

          Equipment                      $200,000

          Total funding                               $2,000,000

     B.   Campus covered walkways; ground and site improvements; equipment and appurtenances.

          Design                         $100,000

          Construction                   $900,000

          Total funding                               $1,000,000

2.   Aiea intermediate school

     A.   Building D courtyard improvements; ground and site improvements; equipment and appurtenances.

          Design                         $500,000

          Construction                 $2,000,000

          Total funding                               $2,500,000

     B.   Covered play court improvements; ground and site improvements; equipment and appurtenances.

          Design                         $575,000

          Construction                 $2,300,000

          Total funding                               $2,875,000

3.   Dole middle school

     A.   Build an open air covered student enrichment/activity area between two buildings.

          Plans                           $50,000

          Design                         $250,000

          Construction                 $3,500,000

          Equipment                      $200,000

          Total funding                               $4,000,000

4.   Kalihi elementary school

     A.   Exterior painting of all school buildings.

          Design                          $50,000

          Construction                   $260,000

          Total funding                                 $310,000

     B.   Repair basketball poles and resurface volleyball/basketball court.

          Design                          $50,000

          Construction                   $250,000

          Total funding                                 $300,000

     C.   Regrade grass landing and playing field.

          Design                          $30,000

          Construction                   $170,000

          Total funding                                 $200,000

5.   Kalihi Uka elementary school

     A.   Install air conditioning on ground floor of the new pre-school in building C.

          Construction                     $7,000

          Equipment                       $21,000

          Total funding                                  $28,000

6.   Kalihi Waena elementary school

     A.   Build utility center with a basketball court equipped for meetings, bathrooms on bottom level, and cardio room, classroom, and equipment room on upper level, including covered walkway.

          Plans                           $15,000

          Design                          $50,000

          Construction                   $800,000

          Equipment                      $100,000

          Total funding                                 $965,000

7.   Major General William R. Shafter elementary school

     A.   Hillside erosion, stabilization, and control; ground and site improvements; equipment and appurtenances.

          Design                         $100,000

          Construction                   $400,000

          Total funding                                 $500,000

8.   Moanalua elementary school

     A.   Electrical upgrade and air conditioning improvements; ground and site improvements; equipment and appurtenances.

          Design                         $100,000

          Construction                   $400,000

          Equipment                      $100,000

          Total funding                                 $600,000

     B.   Multi-purpose innovation center; ground and site improvements; equipment and appurtenances.

          Design                         $320,000

          Construction                 $2,880,000

          Equipment                       $50,000

          Total funding                               $3,250,000

9.   Moanalua middle school

     A.   Student drop-off/pick-up area improvements; ground and site improvements; equipment and appurtenances.

          Design                         $600,000

          Construction                 $1,500,000

          Total funding                               $2,100,000

10.  Webling elementary school

     A.   Expansion of support facilities (administration and library); ground and site improvements; equipment and appurtenances.

          Design                         $800,000

          Construction                 $6,650,000

          Equipment                       $50,000

          Total funding                               $7,500,000

     B.   Campus covered walkways; ground and site improvements; equipment and appurtenances.

          Design                         $100,000

          Construction                   $900,000

          Total funding                               $1,000,000

11.  Wallace Rider Farrington high school

     A.   School redesign project phase II; redesign of the school gym, band, choral, orchestra, and PE facilities.

          Construction                $48,880,000

          Equipment                      $120,000

          Total funding                              $49,000,000

     SECTION 2.  The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriations are made; provided that all moneys from the appropriations that are unencumbered as of June 30, 2020, shall lapse as of that date.

     SECTION 3.  The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended by the department of education.

     SECTION 4.  This Act shall take effect on July 1, 2018.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Fourteenth Senatorial District

 

Description: