HOUSE OF REPRESENTATIVES |
H.B. NO. |
2701 |
TWENTY-NINTH LEGISLATURE, 2018 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE THIRTY-SIXTH REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2018-2019:
1. To be expended by the department of defense:
A. Mililani mauka, Oahu
Plans, design, construction, and equipment for a new emergency alert siren; ground and site improvements; and equipment and appurtenances.
Plans $1,000
Design $1,000
Construction $1,000,000
Equipment $1,000
Total $1,003,000
2. To be expended by the department of education:
A. Kipapa elementary school, Oahu
Design and construction to renovate the stage in the cafeteria; and ground and site improvements.
Design $50,000
Construction $400,000
Total $450,000
B. Kipapa elementary school, Oahu
Design and construction to install stage lighting; and ground and site improvements.
Design $40,000
Construction $180,000
Total $220,000
C. Kipapa elementary school, Oahu
Design and construction to install air conditioning systems in buildings A, D, H, I, L and the portables; and ground and site improvements.
Design $1,000
Construction $799,000
Total $800,000
D. Mililani high school, Oahu
Design and construction to resurface the back and side driveways; and ground and site improvements.
Design $90,000
Construction $350,000
Total $440,000
E. Mililani high school, Oahu
Design and construction to renovate the boys and girls restrooms; and ground and site improvements.
Design $60,000
Construction $200,000
Total $260,000
F. Mililani high school, Oahu
Design and construction to replace the fence at the back of the school; and ground and site improvements.
Design $15,000
Construction $70,000
Total $85,000
G. Mililani high school, Oahu
Design and construction to reroof building W.
Design $23,000
Construction $80,000
Total $103,000
H. Mililani high school, Oahu
Design and construction to reroof building C.
Design $65,000
Construction $263,000
Total $328,000
I. Mililani high school, Oahu
Design and construction to replace the book lockers in building B; and ground and site improvements.
Design $20,000
Construction $95,000
Total $115,000
J. Mililani high school, Oahu
Design and construction to make electrical system improvements in the kitchen located in building R; and ground and site improvements.
Design $12,000
Construction $50,000
Total $62,000
K. Mililani high school, Oahu
Design and construction to reroof buildings F and G.
Design $65,000
Construction $263,000
Total $328,000
L. Mililani high school, Oahu
Design and construction to install ceiling fans in the classrooms.
Design $120,000
Construction $500,000
Total $620,000
M. Mililani high school, Oahu
Design and construction to replace the gymnasium bleachers in building E; and ground and site improvements.
Design $1,000
Construction $32,800
Total $33,800
N. Mililani high school, Oahu
Design and construction to upgrade the fire alarm system.
Design $1,000
Construction $299,000
Total $300,000
Design and construction for a new auditorium; and ground and site improvements.
Design $1,000,000
Construction $29,000,000
Total $30,000,000
P. Mililani ike elementary school, Oahu
Design and construction to install a new bell and PA system including external speakers for the oval area; and ground and site improvements.
Design $75,000
Construction $250,000
Total $325,000
Q. Mililani mauka elementary school, Oahu
Plans, design, and construction to resurface the parking lot; and ground and site improvements.
Plans $1,000
Design $1,000
Construction $698,000
Total $700,000
R. Mililani mauka elementary school, Oahu
Plans, design, and construction for a covered playcourt; and ground and site improvements.
Plans $1,000
Design $1,000
Construction $2,798,000
Total $2,800,000
S. Mililani middle school, Oahu
Design and construction for a new building with fifteen classrooms; and ground and site improvements.
Design $500,000
Construction $9,500,000
Total $10,000,000
T. Mililani uka elementary school, Oahu
Plans, design, and construction for a portable restroom; and ground and site improvements.
Plans $1,000
Design $1,000
Construction $748,000
Total $750,000
U. Mililani uka elementary school, Oahu
Plans, design, and construction for slope stabilization; and ground and site improvements.
Plans $1,000
Design $1,000
Construction $18,000
Total $20,000
V. Mililani uka elementary school, Oahu
Plans, design, and construction to install air conditioning systems in the classrooms; and ground and site improvements.
Plans $1,000
Design $1,000
Construction $298,000
Total $300,000
W. Mililani uka elementary school, Oahu
Design and construction to remodel the cafeteria to be used as an emergency disaster shelter; and ground and site improvements.
Design $1,000
Construction $749,000
Total $750,000
X. Mililani waena elementary school, Oahu
Design and construction to widen the driveway between the main and cafeteria parking lots; and ground and site improvements.
Design $1,000
Construction $749,000
Total $750,000
Y. Mililani waena elementary school, Oahu
Design and construction for a covered walkway next to the parking lot; and ground and site improvements.
Design $1,000
Construction $149,000
Total $150,000
Z. Mililani waena elementary school, Oahu
Design and construction for a covered walkway next to the driveway; and ground and site improvements.
Design $1,000
Construction $149,000
Total $150,000
AA. Mililani waena elementary school, Oahu
Design and construction for a covered lanai between the administration building and library; and ground and site improvements.
Design $1,000
Construction $299,000
Total $300,000
BB. Mililani waena elementary school, Oahu
Design and construction for a covered lanai between the library and cafeteria; and ground and site improvements.
Design $1,000
Construction $299,000
Total $300,000
CC. Mililani waena elementary school, Oahu
Design and construction for an additional classroom and learning space on the second floor of the library; and ground and site improvements.
Design $1,000
Construction $499,000
Total $500,000
DD. Mililani waena elementary school, Oahu
Design and construction to install air conditioning systems in the classrooms.
Design $1,000
Construction $499,000
Total $500,000
3. To be expended by the department of transportation:
A. H-2 freeway, Oahu
Plans, design, and construction to add an additional lane and double-loop on-ramp southbound from Mililani mauka with a pedestrian overpass; traffic mitigation; and ground and site improvements.
Plans $100,000
Design $100,000
Construction $14,800,000
Total funding $15,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2018.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 36th Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 36th Representative District.
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.