     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $68,569,800 or so much thereof as may be necessary, and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2017-2018 for the purpose of capital improvement projects for the forty-fifth representative district, as follows:

I.   To be expended by the department of education:

1. Kipapa Elementary School, Oahu

A. Design and construction for the renovation of the cafeteria stage.

     Design                                  $ 50,000

     Construction                            $400,000

          Total funding                      $450,000

B. Design and construction for the stage lighting.

               Design                                  $ 40,000

               Construction                            $180,000

                   Total funding                      $220,000

C. Design and construction for air conditioning for buildings I, A, D, H, and L, for the portables.

     Design                                  $  1,000

     Construction                            $799,000

          Total funding                      $800,000

2. Mililani High School, Oahu

A. Plans, design, and construction to resurface back and

   side driveways.

     Design                                  $ 90,000

     Construction                            $350,000

          Total funding                      $440,000

B.  Design and construction for renovation of the boys

    and girls bathrooms.

     Design                                  $ 60,000

     Construction                            $200,000

          Total funding                      $260,000

       C.  Design and construction to replace the fence at the

            back of the school.

     Design                                  $ 15,000

     Construction                            $ 70,000

          Total funding                      $ 85,000

       D. Design and construction to reroof building W.

              Design                                  $ 23,000

              Construction                            $ 80,000

                   Total funding                      $103,000

       E. Design and construction to reroof building C.

              Design                                   $ 65,000

              Construction                            $263,000

                   Total funding                      $328,000

       F. Design and construction B RPL book lockers

              Design                                  $ 20,000

              Construction                            $ 95,000

                   Total funding                      $115,000

       G. Design and construction for R kitchen electrical

           improvements.

              Design                                  $ 12,000

              Construction                            $ 50,000

                   Total funding                      $ 62,000

       H. Design and construction to reroof buildings F and G.

              Design                                  $ 65,000

              Construction                            $263,000

                   Total funding                      $328,000

       I. Design and construction for classroom ceiling fans.

              Design                                  $120,000

              Construction                            $500,000

                   Total funding                      $620,000

       J. Design and construction to replace gym bleachers for

           building E.

              Design                                  $  1,000

              Construction                            $ 32,800

                   Total funding                      $ 33,800

       K. Design and construction for fire alarm upgrades.

              Design                                  $  1,000

              Construction                            $299,000

                   Total funding                      $300,000

       L. Design and construction of a new auditorium.

              Design                               $ 1,000,000

              Construction                         $29,000,000

.                  Total funding                   $30,000,000

3. Mililani Waena Elementary School, Oahu

A. Design and construction to widen the driveway between the main parking lot and cafeteria parking lot.

     Design                                  $  1,000

     Construction                            $749,000

          Total funding                      $750,000

B.  Design and construction for a covered walkway next to   

 the parking lot.

Design                                  $  1,000

Construction                            $149,000

     Total funding                      $150,000

C. Design and construction for a covered walkway next to the driveway.

Design                                  $  1,000

Construction                            $149,000

            Total funding                      $150,000

D. Design and construction for a covered lanai between the administration building and the library.

              Design                                  $  1,000

              Construction                            $299,000

                   Total funding                      $300,000

E. Design and construction for a covered lanai between the library and the cafeteria.

            Design                                  $  1,000

            Construction                            $299,000

                 Total funding                      $300,000

F. Design and construction for additional classroom and learning space on the second floor of the library.

            Design                                  $  1,000

            Construction                            $499,000

                 Total funding                      $500,000

G. Design and construction for air conditioning for D-building.

            Design                                  $  1,000

            Construction                            $499,000

                 Total funding                      $500,000

4. Mililani Middle School, Oahu

A. Design and construction of school.

Plans                                $   100,000

Design                               $   100,000

Construction                         $13,300,000

          Total funding                   $13,500,000

5.  Waialua elementary school, Oahu

A. Plans, design, and construction of the old library building for renovation into an auditorium, study area, offices, and teacher's lounge.

Plans                                   $  1,000

Design                                  $  1,000

Construction                            $848,000

            Total funding                      $850,000

B. Plans, design, and construction of covered walkway to portable classrooms.

Plans                                   $  1,000

Design                                  $  1,000

Construction                            $398,000

     Total funding                      $400,000

6. Waialua high and intermediate school, Oahu

A. Plans, design, and construction for the relocation of the visitor parking area.

Plans                                   $  1,000

Design                                  $  1,000

Construction                            $748,000

            Total funding                      $750,000

B. Plans, design, and construction for additional men's and women's restrooms at the football stadium.

Plans                                   $  1,000

Design                                  $  1,000

Construction                            $298,000

     Total funding                      $300,000

C. Plans, design, and construction for a new Innovation Center.

Plans                                   $500,000

Design                                  $500,000

Construction                           $10,000,000

     Total funding                   $11,000,000

II.  To be expended by the department of transportation:

     1. H-2 Freeway, Oahu

          A. Plans, design, and construction for additional lane and double-loop on-ramp southbound from Mililani Mauka with pedestrian overpass; ground and site improvements; equipment and appurtenances.

               Plans                                $   100,000

               Design                                $   100,000

               Construction                         $14,800,000

                   Total funding                   $15,000,000

     SECTION 2.  The appropriations made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriations unencumbered as of June 30, 2020, shall lapse as of that date.

     SECTION 3.  The sums appropriated for the respective capital improvement projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 4.  This Act shall take effect on July 1, 2017.


 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; 45th Representative District

 

Description:

Authorizes the issuance of GO bonds and appropriates funds for capital improvement projects in the 45th representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.