SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2017-2018:
1. To be expended by the department of education:
A. Highlands intermediate school, Oahu
Design and construction for campus-wide electrical upgrades.
Design $300,000
Construction $2,700,000
Total funding $3,000,000
B. Kanoelani elementary school, Oahu
Plans, design, and construction of a portable classroom with a fire lane and hydrant; ground and site improvements.
Plans $250,000
Design $250,000
Construction $3,500,000
Total funding $4,000,000
C. Kipapa elementary school, Oahu
Design and construction to renovate the cafeteria stage.
Design $1,000
Construction $35,000
Total funding $36,000
D. Kipapa elementary school, Oahu
Design and construction to upgrade the cafeteria stage lighting.
Design $1,000
Construction $20,000
Total funding $21,000
E. Kipapa elementary school, Oahu
Construction to install air conditioning systems in buildings A, D, H, I, and L, and portable classrooms.
Construction $1,000,000
Total funding $1,000,000
F. Mililani high school, Oahu
Design and construction to enclose building A's courtyard and extend building A at the school's entrance.
Design $1,000
Construction $2,999,000
Total funding $3,000,000
G. Mililani high school, Oahu
Construction and equipment for improvements to the athletic field including replacing the wooden bleachers with aluminum bleachers; ground and site improvements; and equipment and appurtenances.
Construction $1,100,000
Equipment $100,000
Total funding $1,200,000
H. Mililani high school, Oahu
Construction for a new performing arts facility; ground and site improvements.
Construction $12,000,000
Total funding $12,000,000
I. Mililani Waena elementary school, Oahu
Plans, design, and construction to widen the driveway between the main parking lot and the cafeteria parking lot to create a turnaround area; ground and site improvements.
Plans $5,000
Design $5,000
Construction $990,000
Total funding $1,000,000
J. Mililani Waena elementary school, Oahu
Plans, design, and construction for a covered walkway over the parking lot sidewalk; ground and site improvements.
Plans $5,000
Design $5,000
Construction $190,000
Total funding $200,000
K. Mililani Waena elementary school, Oahu
Plans, design, and construction for a covered walkway over the driveway sidewalk; ground and site improvements.
Plans $5,000
Design $5,000
Construction $190,000
Total funding $200,000
L. Mililani Waena elementary school, Oahu
Plans, design, and construction for a covered lanai between the administration and library buildings; ground and site improvements.
Plans $5,000
Design $5,000
Construction $340,000
Total funding $350,000
M. Mililani Waena elementary school, Oahu
Plans, design, and construction for a covered lanai between the library and cafeteria buildings; ground and site improvements.
Plans $5,000
Design $5,000
Construction $340,000
Total funding $350,000
N. Mililani Waena elementary school, Oahu
Plans, design, and construction of a second floor for the library.
Plans $5,000
Design $5,000
Construction $4,990,000
Total funding $5,000,000
O. Mililani Waena elementary school, Oahu
Construction to install air conditioning systems in the remaining classrooms in building D.
Construction $500,000
Total funding $500,000
P. Pearl City high school, Oahu
Design and construction to clear drains and improve drainage along the stadium access road.
Design $100,000
Construction $900,000
Total funding $1,000,000
Q. Pearl City high school, Oahu
Plans, design, and construction for campus-wide electrical upgrades.
Plans $250,000
Design $250,000
Construction $4,500,000
Total funding $5,000,000
R. Pearl City high school, Oahu
Plans, design, and construction to repave the KLM parking lot, cafeteria parking lot, and road to the band room.
Plans $100,000
Design $100,000
Construction $1,800,000
Total funding $2,000,000
S. Pearl City high school, Oahu
Design and construction to replace the auditorium's downspouts and improve drainage.
Design $25,000
Construction $75,000
Total funding $100,000
T. Waipahu high school, Oahu
Design and construction for a new classroom building; ground and site improvements.
Design $1,000
Construction $14,999,000
Total funding $15,000,000
U. Waipahu intermediate school, Oahu
Design and construction for a new classroom building; ground and site improvements.
Design $1,000
Construction $21,999,000
Total funding $22,000,000
V. Waipahu intermediate school, Oahu
Design and construction for additional multi-purpose play courts; ground and site improvements.
Design $1,000
Construction $2,999,000
Total funding $3,000,000
W. Waikele elementary school, Oahu
Design and construction for a new building with six classrooms to accommodate the growing student body; ground and site improvements.
Design $5,000
Construction $6,995,000
Total funding $7,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2017.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 37th Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 37th Representative District.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.