SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2011-2012:
1. To be expended by the department of education:
A. McKinley high school, Oahu
Plans, design, construction, and equipment for electrical upgrades to PH 1 F.
Plans $1,000
Design $1,000
Construction $1,000
Equipment $250,000
Total funding $253,000
B. McKinley high school, Oahu
Plans,
design, construction, and equipment for electrical upgrades.
Plans $1,000
Design $1,000
Construction $997,000
Equipment $1,000
Total funding $1,000,000
C. McKinley high school, Oahu
Plans, design, construction, and equipment for softball stadium.
Plans $1,000
Design $1,000
Construction $2,500,000
Equipment $1,000
Total funding $2,503,000
D. Central middle school, Oahu
Plans, design, construction, and equipment for campus security improvements.
Plans $1,000
Design $1,000
Construction $1,000
Equipment $1,000
Total funding $4,000
E. Central middle school, Oahu
Plans, design, construction, and equipment for reroofing of building C.
Plans $1,000
Design $1,000
Construction $1,000
Equipment $1,000
Total funding $4,000
F. Central middle school, Oahu
Plans, design, construction, and equipment for reroofing of building D.
Plans $1,000
Design $1,000
Construction $1,000
Equipment $1,000
Total funding $4,000
G. Central middle school, Oahu
Plans, design, construction, and equipment for electrical upgrades.
Plans $1,000
Design $1,000
Construction $1,000
Equipment $1,000
Total funding $4,000
H. Stevenson middle school, Oahu
Plans and design for a master plan.
Plans $1,000
Design $550,000
Total funding $551,000
I. Stevenson middle school, Oahu
Plans and design for a multi-purpose recreational facility.
Plans $1,000
Design $1,500,000
Total funding $1,501,000
J. Stevenson middle school, Oahu
Plans, design, construction, and equipment for building A, multi-purpose science learning center.
Plans $1,000
Design $1,000
Construction $7,200,000
Equipment $1,000
Total funding $7,203,000
K. Washington middle school, Oahu
Plans, design, and equipment for electrical upgrades to the cafeteria dining room.
Plans $1,000
Design $1,000
Equipment $50,000
Total funding $52,000
L. Washington middle school, Oahu
Plans, design, and equipment for electrical upgrades to the kitchen.
Plans $1,000
Design $1,000
Equipment $55,000
Total funding $57,000
M. Washington middle school, Oahu
Plans, design, and equipment for electrical upgrades to building B.
Plans $1,000
Design $1,000
Equipment $75,000
Total funding $77,000
N. Kaiulani elementary school, Oahu
Plans, design, construction, and equipment for Americans with Disabilities Act transition accessibility.
Plans $1,000
Design $1,000
Construction $375,000
Equipment $1,000
Total funding $378,000
O. Kaiulani elementary school, Oahu
Plans, design, construction, and equipment to install air conditioning.
Plans $1,000
Design $1,000
Construction $3,500,000
Equipment $1,000
Total funding $3,503,000
P. Kauluwela elementary school, Oahu
Plans, design, and equipment to install security cameras around campus.
Plans $1,000
Design $1,000
Equipment $6,000
Total funding $8,000
Q. Likelike elementary school, Oahu
Plans, design, construction, and equipment to install parking lights and other security improvements.
Plans $1,000
Design $1,000
Construction $250,000
Equipment $1,000
Total funding $253,000
R. Likelike elementary school, Oahu
Plans, design, construction, and equipment for electrical upgrades.
Plans $1,000
Design $1,000
Construction $465,000
Equipment $1,000
Total funding $468,000
S. Likelike elementary school, Oahu
Plans,
design, construction, and equipment to install air conditioning.
Plans $1,000
Design $1,000
Construction $3,500,000
Equipment $1,000
Total funding $3,503,000
T. Royal school, Oahu
Plans, design, construction, and equipment to improve security by installing grills and locked gates to building B.
Plans $1,000
Design $1,000
Construction $170,000
Equipment $1,000
Total funding $173,000
U. Royal school, Oahu
Plans, design, construction, and equipment to replace building C.
Plans $1,000
Design $1,000
Construction $2,000,000
Equipment $1,000
Total funding $2,003,000
2. To be expended by the department of accounting and general services:
A. Hawaii theatre center, Oahu
Plans, design, construction, and equipment for the Hawaii theatre center.
Plans $1,000
Design $1,000
Construction $1,575,000
Equipment $1,000
Total funding $1,578,000
B. State capitol building, Oahu
Design and construction to upgrade the water circulation system and replace the lining system in the reflection pools.
Design $1,000
Construction $7,899,000
Total funding $7,900,000
3. To be expended by the Hawaii public housing authority:
A. Mayor Wright homes, Oahu
Plans,
design, construction, and equipment to maintain the water heater system for the
Mayor Wright homes.
Plans $1,000
Design $1,000
Construction $600,000
Equipment $1,000
Total funding $603,000
B. Mayor Wright homes, Oahu
Plans, design, construction, and equipment for solar removal, roof replacement, instant hot water system, painting, and site improvements for Mayor Wright homes.
Plans $1,000
Design $1,000
Construction $2,500,000
Equipment $1,000
Total funding $2,503,000
4. To be expended by the university of Hawaii:
A. Honolulu community college, Oahu
Plans, design, construction, and equipment to improve Kokea street to meet city and county of Honolulu sidewalk standards.
Plans $1,000
Design $1,000
Construction $1,500,000
Equipment $1,000
Total funding $1,503,000
B. Honolulu community college, Oahu
Plans, design, construction, and equipment to pave the incinerator lot, including drainage, hazmat, and lighting.
Plans $1,000
Design $1,000
Construction $7,000,000
Equipment $1,000
Total funding $7,003,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act. SECTION 3. This Act shall take effect on July 1, 2011.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; Twenty-eighth Representative District
Description:
Appropriates funds for capital improvement projects to benefit the twenty-eighth representative district.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.