SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2010-2011:
To be expended by the department of education:
A. Lincoln elementary school, Oahu
Complete upgrade of the air conditioning project underway for buildings A, B, D, and E.
Plans and design $ 500,000
Construction, labor, and supplies 6,000,000
Total Funding $ 6,500,000
Resurface kindergarten playground behind building G by removing sand and installing safety matting.
Plans, design, construction,
labor, and supplies $ 75,000
Total Funding $ 75,000
B. Nuuanu elementary school, Oahu
Partition in cafeteria for use as a classroom.
Plans $ 2,000
Design 2,000
Construction 10,000
Equipment 25,000
Total Funding $ 39,000
Slip prevention improvement.
Plans $ 2,000
Design 2,000
Construction 10,000
Equipment 10,000
Total Funding $ 24,000
Resurface open gym floor.
Plans $ 5,000
Construction 15,000
Equipment 20,000
Total Funding $ 40,000
C. Roosevelt high school, Oahu
Resurvey of land under the school and development of a master plan.
Plans $ 250,000
Total Funding $ 250,000
Renovation and expansion of gym locker areas.
Plans $ 100,000
Design 200,000
Construction 5,000,000
Total Funding $ 5,300,000
Renovation and expansion of the band room.
Plans $ 100,000
Design 200,000
Construction 4,000,000
Total Funding $ 4,300,000
Plan, design, and construction of a multi-level parking structure.
Plans $ 200,000
Design 200,000
Construction 3,500,000
Total Funding $ 3,900,000
D. Royal elementary school, Oahu
Installation of grills and locked gates to improve security for building B.
Design $ 10,000
Construction 85,000
Equipment 75,000
Total funding $ 170,000
Replacement of building C due to structural damage.
Plans $ 10,000
Design 10,000
Construction 1,980,000
Total funding $ 2,000,000
E. Stevenson middle school, Oahu
Initial plan and design of a master plan.
Plans $ 225,000
Design 225,000
Total funding $ 450,000
Plans, design, and construction of building A, a multi-purpose science learning center.
Plans $ 100,000
Design 700,000
Construction 6,350,000
Equipment 50,000
Total funding $ 7,200,000
Plans and design of a multi-purpose recreational facility.
Plans $ 10,000
Design 1,490,000
Total funding $ 1,500,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2010.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 26th Representative District