HOUSE OF REPRESENTATIVES

H.B. NO.

2450

TWENTY-FIFTH LEGISLATURE, 2010

H.D. 1

STATE OF HAWAII

S.D. 1

 

Proposed

 

 

 

A BILL FOR AN ACT

 

 

RELATING TO RENEWABLE ENERGY FACILITIES.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  Act 173, Session Laws of Hawaii 2009 (Act 173), recognized that to develop and finance renewable energy facilities, a site for the facilities and access to the site must often be leased, granted as an easement, or mortgaged to provide financing for the project.  However, renewable energy projects may require site acreage or configurations that do not coincide with existing, already subdivided lot boundaries.  For instance, land required for a project may constitute only a portion of a large legal lot, and it may be impractical or undesirable to lease or convey the entire legal lot for a renewable energy project, or to encumber the entire legal lot with a mortgage that provides financing for the project.      Therefore, the purpose of Act 173 was to facilitate the financing and development of renewable energy projects by allowing leases and easements pertaining to renewable energy projects, together with mortgages and other conveyances as security for finance, to be created, enforced, and recorded, without requiring the landowner to obtain formal subdivision approval, and instead requiring approval for exemption from subdivision requirements, from the applicable county or other approving agency.

     However, the application of Act 173 was limited to solar energy facilities permitted under section 205-2(d)(6), Hawaii Revised Statutes, on land with soil classified by the land study bureau's detailed land classification as overall (master) productivity rating class D or E or wind energy facilities and related appurtenances located within a conservation state land use district.  The legislature now finds that there may be other renewable energy facilities that have been approved or permitted by the appropriate agencies that are required to go through the subdivision process threatening the financial viability of these projects.

     Therefore, the purpose of this Act is to extend the applicability of Act 173 to include any renewable energy facilities approved by the land use commission or county planning commission under chapter 205, Hawaii Revised Statutes, or any renewable energy facilities permitted or approved by the board of land and natural resources under chapter 183C, Hawaii Revised Statutes.  Further, it is the intent of the legislature that the remaining land (i.e., the portion of the original legal lot of record less the area used for the renewable energy facility) receive the same legal lot status as the renewable energy parcel and be recognized as a legal lot of record by the counties, thus allowing for those remaining lands to be put to other use and to receive mortgage financing and title insurance.

     SECTION 2.  Section 201N-14, Hawaii Revised Statutes, is amended to read as follows:

     "[[]§201N-14[]]  Exemption from subdivision requirements.  (a)  Notwithstanding any other law or ordinance to the contrary:

     (1)  Lands within the urban, rural, agricultural, or conservation state land use district may be leased; and

     (2)  Easements or other possessory interests, whether exclusive or non-exclusive, may be created and granted over lands within the urban, rural, agricultural, or conservation state land use district,

for the purpose of developing and financing a renewable energy [project] facility or accessing a renewable energy [project] facility that is a permitted use in the district, even if the leased land or the easement or other possessory interest area has not been subdivided as a separate subdivided lot or easement.  In order to facilitate the productive use of the land other than the land on which the renewable energy facility is located or from which it is accessed, the remaining portion of the parcel from which the land derives shall be entitled to the benefit of this section for uses otherwise permitted in the district.  Leases [and], easements, and other possessory interests authorized by this section shall be valid leases [and], easements, and other possessory interests for all purposes, but the exemption from subdivision requirements authorized by this section shall be subject to the requirements and limitations set forth in subsection (d).

     (b)  Without limiting the generality of subsection (a), the following may be performed without complying with subdivision requirements:

     (1)  All or a portion of a legal lot may be leased as a site for a renewable energy [project] facility or access to the [project] facility and the remainder of the legal lot may be leased for uses otherwise permitted in the district;

     (2)  Easements or other possessory interests, whether exclusive or nonexclusive, may be granted to use all or a portion of the legal lot as a renewable energy [project] facility site or access to the [project;] facility and easements or other possessory interests, whether exclusive or non-exclusive, may be granted on the remainder of the legal lot for uses otherwise permitted in the district;

     (3)  Maps, leases, licenses, grants of easements, or other instruments providing for the right to use all or a portion of a legal lot as delineated on a map for a renewable energy [project] facility site or access to the [project] facility or for the remainder of the legal lot may be recorded; and

     (4)  Mortgages and other security interests may be granted with respect to any lease [or], easement, or other possessory interest created pursuant to this section, and the holders of such mortgages or other security interests may foreclose upon the lease [or], easement, or other possessory interest covered and otherwise enforce the terms of the mortgage and security documents, subject to compliance with applicable laws other than subdivision requirements.

     (c)  The land court, bureau of conveyances, and other governmental agencies shall accept for filing and recording all instruments and maps pertaining to leases, easements, other possessory interests, mortgages, and other security documents authorized pursuant to this section.

     (d)  The exemption from subdivision requirements authorized by this section shall only apply to leases [and], easements, and other possessory interests that meet the following requirements and shall be subject to the following limitations:

     (1)  The lease [or], easement, or other possessory interest relating to a renewable energy facility shall restrict the use of the leased land or easement area to the development and operation of a renewable energy [project;] facility; provided that, to comply with section 205-4.6, agricultural uses and activities shall not be restricted on agricultural land;

     (2)  The lease, easement, or other possessory interest relating to a renewable energy facility shall have an initial term of at least twenty years;

     (3)  With respect to leases, easements, and other possessory interests relating to a renewable energy facility on lands within urban and rural state land use districts, the exemption from subdivision requirements provided in this section shall be only for renewable energy facilities using or producing biomass or biofuels, including the appurtenances associated with the production and transmission of energy;

     (4)  With respect to leases [and], easements, and other possessory interests relating to a renewable energy facility on lands within an agricultural state land use district, the exemption from subdivision requirements provided by this section shall be for [solar]:

(A)  Solar energy facilities permitted under section 205-2(d)(6), on land with soil classified by the land study bureau's detailed land classification as overall (master) productivity rating class D or E;

(B)  Any renewable energy facilities approved by the land use commission or county planning commission under chapter 205; and

         (C)  Any renewable energy facility using or producing biomass or biofuels;

    [(4)] (5)  With respect to leases [and], easements, and other possessory interests relating to a renewable energy facility on lands within a conservation state land use district, the exemption from subdivision requirements provided by this section shall be for [wind]:

(A)  Wind energy facilities, including the appurtenances associated with the production and transmission of wind-generated energy; and

(B)  Any renewable energy facilities permitted or approved by the board of land and natural resources under chapter 183C;

    [(5)] (6)  With respect to leases, easements, and other possessory interests on the remaining portion of the legal lot, other than where the renewable energy facility is located or from which it is accessed, the exemption from subdivision requirements provided in this section shall be for the entirety of that remaining portion of the legal lot; and

     (7)  The county agency charged with administering subdivisions in the county in which the renewable energy [project] facility is to be situated or, if the land is in a conservation state land use district, the department of land and natural resources, shall approve the exemption from subdivision requirements within ninety days after the [project's] facility's developer and the owner of the land on which the renewable energy [project] facility is to be situated have submitted the conceptual schematics or preliminary plans and specifications for the renewable energy [project] facility to the county agency or the department of land and natural resources, and have provided to [such] the county agency or the department of land and natural resources, as applicable, a certification and agreement that all applicable and appropriate environmental reviews and permitting shall be completed prior to commencement of development of the renewable energy [project.] facility.  If, on the ninety-first day, an exemption has not been approved, it shall be deemed disapproved by the county agency or the department of land and natural resources, whichever is applicable.

     (e)  Nothing in this section shall:

     (1)  Exempt the actual development, construction, or operation of any use, project, facility, or improvement from any applicable state or county laws, ordinances, restrictions, permits, or approvals, including restrictions on allowable uses or conditions and requirements for adequate infrastructure or mitigation measures;

     (2)  Exempt renewable energy [projects] facilities from any permit or approval process under chapter 183C, 205, 205A, or 343;

     (3)  Exempt from subdivision requirements the conveyance of any fee interest in land; or

     (4)  Prevent any agency or authority that issues permits or approvals for renewable energy [projects] facilities from imposing reasonable and appropriate restrictions on the type of siting, development, construction, and operation of a renewable energy [project] facility to protect agricultural resources and activities, the environment, natural resources, cultural resources and activities, or the health, safety, and welfare of the State.

     (f)  All agencies and authorities that issue permits or approvals for renewable energy [projects] facilities may adopt rules or procedures to:

     (1)  Determine the type of renewable energy [project] facility that may be allowed within an agricultural or conservation district;

     (2)  Determine criteria for the appropriate siting of the renewable energy [project] facility within an urban, rural, agricultural, or conservation district; and

     (3)  Identify mitigation measures applicable to renewable energy [projects] facilities to protect agricultural resources and activities, the environment, natural resources, cultural resources and activities, health, safety, and welfare of the State.

     (g)  This section is not intended to diminish the discretion of any agency or any authority to approve or disapprove any permit application."

     SECTION 3.  Statutory material to be repealed is bracketed and stricken.  New statutory material is underscored.

     SECTION 4.  This Act shall take effect upon its approval, and shall be repealed on the same date as section 2 of Act 173, Session Laws of Hawaii 2009.

 



 

 

Report Title:

Renewable Energy Facilities; Subdivision Requirement; Exemptions

 

Description:

Clarifies that the exemption from subdivision requirements for leases, easements, and other possessory interests for renewable energy facilities applies to renewable energy facilities on urban, rural, or agricultural land approved by the land use commission and county planning commissions, and renewable energy facilities on conservation land permitted by the board of land and natural resources.  (SD1)

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.