Report Title:
Department of Education Facilities; Capital Improvement Projects
Description:
Appropriates funds for various capital improvement projects for the Department of Education.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
882 |
TWENTY-FIFTH LEGISLATURE, 2009 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO THE EDUCATION REVITALIZATION ACT OF 2009.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2009-2010:
1. To be expended by the department of education:
A. Lump sum capital improvement project – project positions, statewide.
Plans $9,600,000
Total funding $9,600,000
B. Lump sum capital improvement project – school building improvements, statewide.
Construction $175,000,000
Total funding $175,000,000
C. Lump sum capital improvement project – classroom renovations, statewide.
Construction $30,000,000
Total funding $30,000,000
D. Lump sum capital improvement project – project adjustment, statewide.
Construction $4,000,000
Total funding $4,000,000
E. Lump sum capital improvement project – relocate/construct temporary facilities, statewide.
Construction $17,000,000
Total funding $17,000,000
F. Lump sum capital improvement project – architectural barrier removal, statewide.
Construction $4,000,000
Total funding $4,000,000
G. Lump sum capital improvement project – Americans with Disabilities Act transition, statewide.
Construction $4,000,000
Total funding $4,000,000
H. Lump sum capital improvement project – asbestos/lead removal, statewide.
Construction $2,000,000
Total funding $2,000,000
I. Lump sum capital improvement project – special education renovations, statewide.
Construction $2,000,000
Total funding $2,000,000
J. Lump sum capital improvement project – gender equity projects, statewide.
Construction $4,000,000
Total funding $4,000,000
K. Lump sum capital improvement project – fire protection improvements, statewide.
Construction $1,000,000
Total funding $1,000,000
L. Lump sum capital improvement project – health and safety improvements, statewide.
Construction $1,000,000
Total funding $1,000,000
M. Lump sum capital improvement project – science facilities upgrades, statewide.
Construction $21,000,000
Total funding $21,000,000
N. Lump sum capital improvement project – electrical upgrades, statewide.
Construction $30,000,000
Total funding $30,000,000
O. Lump sum capital improvement project – minor renovations, statewide.
Construction $6,000,000
Total funding $6,000,000
P. Lump sum capital improvement project – noise/heat abatement, statewide.
Construction $20,000,000
Total funding $20,000,000
Q. Lump sum capital improvement project – telecommunications, statewide.
Construction $4,000,000
Total funding $4,000,000
R. Lump sum capital improvement project – master plan, statewide.
Land acquisition $1,000,000
Total funding $1,000,000
S. Lump sum capital improvement project – state/district improvements, statewide.
Construction $500,000
Total funding $500,000
T. Lump sum capital improvement project – energy improvements, statewide.
Construction $10,000,000
Total funding $10,000,000
U. Ewa makai middle school, Oahu
Plans, land, design, construction, and equipment for a new middle school.
Plans $1,000
Land $1,000
Design $1,000
Construction $17,796,000
Equipment $1,000
Total funding $17,800,000
V. James Campbell high school, Oahu
Plans, design, and construction for a classroom building.
Plans $1,000
Design $1,000
Construction $4,498,000
Total funding $4,500,000
W. Maui Waena intermediate school, Maui
Plans, design, and construction for classroom building.
Plans $1,000
Design $1,000
Construction $1,198,000
Total funding $1,200,000
X. Keaau middle school, Hawaii
Plans, design, and construction for classroom building.
Plans $1,000
Design $1,000
Construction $3,998,000
Total funding $4,000,000
Y. Lanai high and elementary school, Lanai
Plans, design, and construction for classroom building.
Plans $1,000
Design $1,000
Construction $4,498,000
Total funding $4,500,000
Z. Kapolei II elementary school, Oahu
Plans, land, design, construction, and equipment for a new elementary school.
Plans $1,000
Land $1,000
Design $1,000
Construction $43,996,000
Equipment $1,000
Total funding $44,000,000
AA. East Kapolei middle school, Oahu
Plans, land, design, construction, and equipment for a new middle school.
Plans $1,000
Land $1,000
Design $1,000
Construction $94,996,000
Equipment $1,000
Total funding $95,000,000
BB. East Kapolei high school, Oahu
Plans, land, design, construction, and equipment for a new high school.
Plans $1,000
Land $1,000
Design $1,000
Construction $5,996,000
Equipment $1,000
Total funding $6,000,000
CC. Schofield area elementary school, Oahu
Plans, land, design, construction, and equipment for a new elementary school.
Plans $1,000
Land $1,000
Design $1,000
Construction $19,996,000
Equipment $1,000
Total funding $20,000,000
DD. Royal Kunia elementary school, Oahu
Plans, land, design, construction, and equipment for a new elementary school.
Plans $1,000
Land $1,000
Design $1,000
Construction $3,756,000
Equipment $1,000
Total funding $3,760,000
EE. Kahuku high and intermediate school, Oahu
Plans, design, and construction for flood improvements.
Plans $1,000
Design $1,000
Construction $4,998,000
Total funding $5,000,000
FF. Konawaena middle school, Hawaii
Construction for locker/shower building.
Construction $10,400,000
Total funding $10,400,000
GG. Liliuokalani building, Oahu
Equipment and construction for backup generator.
Construction $499,000
Equipment $1,000
Total funding $500,000
HH. Kualapuu elementary school, Molokai
Plans, Design, and construction for water line.
Plans $1,000
Design $1,000
Construction $3,218,000
Total funding $3,220,000
II. McKinley high school, Oahu
Plans, design, and construction for building 857 renovations.
Plans $1,000
Design $1,000
Construction $4,998,000
Total funding $5,000,000
JJ. Farrington high school, Oahu
Plans, design, and construction for campus modernization.
Plans $1,000
Design $1,000
Construction $26,998,000
Total funding $27,000,000
KK. Kau high and Pahala elementary school, Hawaii
Plans, design, and construction for classroom building.
Plans $1,000
Design $1,000
Construction $11,928,000
Total funding $11,930,000
LL. Kohala high school, Hawaii
Plans, design, and construction for classroom building.
Plans $1,000
Design $1,000
Construction $15,498,000
Total funding $15,500,000
MM. Kapaa elementary school, Hawaii
Construction for library.
Construction $6,480,000
Total funding $6,480,000