Report Title:

CIP – 17th representative district

 

Description:

Capital improvement projects for 17th representative district.

 


HOUSE OF REPRESENTATIVES

H.B. NO.

3448

TWENTY-FOURTH LEGISLATURE, 2008

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT


 

 

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE seventeenth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of  $      , or so much thereof as may be necessary, and the same sum, or so much thereof as may be necessary, is appropriated for fiscal year 2007-2008 for the purpose of capital improvement projects for the nineteenth representative district, as follows:

I.   To be expended by the Department of Transportation:

     A.   Maunalua Bay, Oahu

          (1)  Plans, design, and construction of a commercial loading dock.

          Plans                                        $40,000

          Design                                       $70,000

          Construction                               $252,540

          Total Funding                              $362,540

II.  To be expended by the Department of Education:

     A.   Kaiser High School, Oahu

          (1)  Design and construction of girls varsity locker room facilities in compliance with Title IX requirements.

          Planning                                   $100,000

          Design                                     $300,000

          Construction                              $3,600,000

          Total Funding                             $4,000,000

          (2)  New track.

          Planning                                     $50,000

          Design                                     $150,000

          Construction                              $1,800,000

          Total Funding                             $2,000,000

          (3)  Renovations to come into compliance with ADA,                  campus-wide

          Total Funding                              $375,000

          (4)  Air conditioning of the school

          Total Funding                            $10,000,000

     B.   Hahaione Elementary School, Oahu

          (1)  Electrical upgrades to school.

          Total Funding                              $511,000

          (2)  Architectural barrier removal.

          Total Funding                              $605,000

     C.   Kamiloiki Elementary School, Oahu

          (1)  Electrical upgrades to school.

          Total funding                              $511,000

          (2)  Renovations to meet ADA accessibility standards, campus-wide

          Total Funding                              $412,500

     D.   Koko Head Elementary School, Oahu

          (1)  Reroofing of two buildings.

          Construction                               $328,000

          Total Funding                              $328,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2008.

 

 

INTRODUCED BY:

_____________________________