Report Title:

CIP; 22nd Representative District

 

Description:

Appropriates funds for capital improvement projects for the benefit of the 22nd representative district.

 


HOUSE OF REPRESENTATIVES

H.B. NO.

3234

TWENTY-FOURTH LEGISLATURE, 2008

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT


 

 

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE TWENTY-SECOND REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The following sums or so much thereof as shall be sufficient to finance the projects listed in this Act are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2008-2009:

     1.   To be expended by the department of education:

     A.   Hokulani elementary school, Oahu

Design and construction for accessible parking and shelter to cover disabled parking stalls.

          Design                             $1,000

          Construction                      $199,000

          Total funding                     $200,000

     B.   Hokulani elementary school, Oahu

Design, construction, and equipment for Americans With Disabilities Act (ADA) transition accessibility bathrooms.

          Design                             $1,000

          Construction                      $373,000

          Equipment                           $1,000

          Total funding                     $375,000

     C.   George Washington middle school, Oahu

          Equipment for security cameras.

          Equipment                         $25,000

          Total funding                     $25,000

     D.   George Washington middle school, Oahu

          Equipment for phone system upgrades.

          Equipment                         $25,000

          Total funding                     $25,000

     E.   George Washington middle school, Oahu

Design, construction, and equipment for retrofitting three classrooms into science labs.

          Design                             $1,000

          Construction                      $748,000

          Equipment                          $1,000

          Total funding                     $750,000

     F.   George Washington middle school, Oahu

Design, construction, and equipment for retrofitting woods classroom into a technical education center.

          Design                             $1,000

          Construction                      $148,000

          Equipment                          $1,000

          Total funding                     $150,000

     G.   George Washington middle school, Oahu

Design, construction, and equipment for retrofitting keyboarding classroom into a media production studio.

          Design                             $1,000

          Construction                      $148,000

          Equipment                          $1,000

          Total funding                     $150,000

     H.   King William C. Lunalilo elementary school, Oahu

Plans, design, construction, and equipment for electrical evaluation and electrical panel and circuitry upgrade.

          Plans                              $1,000

          Design                             $1,000

          Construction                      $397,000

          Equipment                          $1,000

          Total funding                     $400,000

     I.   King William C. Lunalilo elementary school, Oahu

Plans, design, construction, and equipment for a school-wide water sprinkler system.

          Plans                              $1,000

          Design                             $1,000

          Construction                      $497,000

          Equipment                          $1,000

          Total funding                     $500,000

     J.   Kuhio elementary school, Oahu

          Design and construction to extend office space.

          Design                              $1,000

          Construction                      $39,000

          Total funding                     $40,000

     K.   Kuhio elementary school, Oahu

Design and construction to extend the library to include a teacher workroom.

          Design                              $1,000

          Construction                      $49,000

          Total funding                     $50,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

     SECTION 3.  This Act shall take effect on July 1, 2008.

 

INTRODUCED BY:

_____________________________