Report Title:

CIP; 13th Representative District

Description:

Appropriates funds for capital improvement projects for the 13th representative district.

HOUSE OF REPRESENTATIVES

H.B. NO.

3211

TWENTY-THIRD LEGISLATURE, 2006

 

STATE OF HAWAII

 


 

A BILL FOR AN ACT

 

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE THIRTEENTH REPRESENTATIVE DISTRICT.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2006-2007.

1. To be expended by the department of accounting and general services:

A. Haiku elementary school, Maui

Design, construction, and equipment for six-classroom building, ground, and site improvements.

Total funding $3,159,000

B. Hana high and elementary schools, Maui

Design, construction, and equipment for administration building. Ground and site improvements and electrical upgrade. $3,264,000

Plans, design, and construction of auditorium, including site improvements. $6,000,000

Total funding $ 9,264,000

C. Kaunakakai elementary school, Molokai

Various improvements.

Total funding $ 355,000

D. Keanae school, Maui

Sidewalk repairs.

Total funding $         

E. Kilohana elementary school, Molokai

Design and construction of cafeteria and library.

Total funding $ 5,410,000

F. Kualapuu elementary school, Molokai

Various improvements.

Total funding $         

G. Lanai high and elementary schools, Lanai

Design of classroom building and improvements. $ 2,719,000

Construction of six-classroom building. 9,000,000

Total funding $11,719,000

H. Maunaloa elementary school, Molokai

Improvements, design, and construction of administration and library buildings, and four-classroom building.

Total funding $10,224,000

I. Molokai high and intermediate schools, Molokai

Improvements, design, and construction of bus drop off and turn around areas, and four-classroom building. $ 743,000

Plans, design, and construction for new library building. $          

Total funding $          

J. Paia elementary school, Maui

Design and construction of a new cafeteria building, special education preschool, and improvements.

Total funding $2,860,000

K. Hana affordable housing project, Maui

Plans, design, and construction of affordable housing on lands donated by Hana ranch.

Total funding $4,100,000

L. Hana community health center, Maui

Plans, design, and construction for a hemodialysis services center. $1,000,000

Various renovations. $         

Total funding $         

M. Hana health nutrition training center, Maui

Plans, design, and construction of a health nutrition center. $ 500,000

N. Hana senior housing, Maui

Land acquisition, plans, design, and construction for senior housing.

Total funding $5,000,000

O. Kapaakea drainage improvement, Molokai

Improved drainage to avert flood damage and potential state liability.

Total funding $4,000,000

P. Kalaupapa museum, Molokai

Plans, land acquisition, design, construction, and equipment for a museum to perpetuate Kalaupapa's unique history and to store information, documents, and mementos of Kalaupapa's history and culture.

Total funding $ 585,000

Q. Lanai community hospital, Lanai

Construction, equipment to renovate kitchen. $ 25,000

Design and construction for a certified kitchen. $ 81,000

Total funding $ 106,000

R. Lanai veterans cemetery, Lanai

Plans, design, and construction, and equipment for a water storage and irrigation system.

Total funding $ 100,000

S. Molokai electric plant, Molokai

Design and equipment for telecommunications development.

Total funding $ 150,000

T. Molokai general hospital, Molokai

Design and construction to expand and improve the hospital. $         

Various renovations. $         

Total funding $1,600,000

U. Molokai veterans center, Molokai

Plans, design, and construction for a Molokai veterans center.

Total funding $         

2. To be expended by the department of transportation:

A. Bikeway pullout, Maui

Plans, design, and construction of bikeway pullout for downhill bikers.

Total funding $ 200,000

B. Ferry system improvements, Lanai and Molokai

Various improvements.

Total funding $        

C. Hana airport, Maui

Plans, design, and construction for the airport, including an environmental assessment.

Total funding $        

D. Hana highway improvements, Maui

Construction for widening the existing roadway from Uakea road to Keawa place and construction of safety improvements.

Total funding $        

E. Hana highway sidewalks, Maui

Plans, design, and construction of sidewalks along Hana highway fronting Hana high school.

Total funding $1,000,000

F. Hana highway rockfall mitigation, Maui

Construction to remove overhanging, protruding, and unstable rocks from the slopes above Hana highway.

Total funding $        

G. Kalaupapa airport, Molokai

Plans, design, and construction, including an environmental assessment and part 139 compliance improvements to the airport aircraft rescue and fire fighting station.

Total funding $        

H. Kalaupapa pier, Molokai

Design work for the replacement of bulkhead wall and major repairs to the pier.

Total funding $ 750,000

I. Kamehameha V highway, Molokai

Improvements and land acquisition for replacement of Kawela stream bridge, including sidewalks. $        

Land acquisition for replacement of Makakupaia stream bridge to include bridge railings and other improvements. $        

Land acquisition and design to upgrade and improve existing culvert, other drainage facilities, shoulders and other improvements at mile post 12.5. $        

Total funding $        

J. Kaumalapau harbor, Lanai

Design and construction for improvements to the pier, yard, lighting, utilities, and other related improvements.

Total funding $        

K. Lanai airport, Lanai

Construction for airport aircraft rescue and fire fighting station. $        

Various improvements. $        

Total funding $        

L. Maunaloa highway slope stabilization, Molokai

Design for stabilization of embankment at mile post 13 and mile post 14.3.

Total funding $1,925,000

M. Molokai airport, Molokai

Construction for Molokai airport aircraft rescue and fire fighting station improvements. $         

Culvert design for part 139 compliance. $         

Total funding $         

N. Molokai bridge, Molokai

Plans, design, and construction for a bridge next to Meyer's place.

Total funding $ 221,000

O. Paia bypass, Maui

Plans for alternative traffic improvements in Paia town.

Total funding $1,500,000

P. State highway improvements, Molokai

Guardrail and shoulder improvements on state highways including design and construction of asphalt concrete paved shoulders and installation and upgrading of existing guardrails.

Total funding $         

3. To be expended by the department of agriculture:

D. Molokai irrigation system, Molokai

Plans, design, and construction of capital improvements to the irrigation system. $2,000,000

Improve transmission line intakes, clean blowouts repairs, and maintenance of meters. 100,000

Total funding $2,100,000

4. To be expended by the department of land and natural resources:

A. Agricultural park, Lanai

Plans, design, and construction to develop infrastructure for an agricultural park.

Total funding $ 450,000

B. Hana wharf and small boat harbor, Maui

Renovation of the Hana wharf.

Total funding $15,000,000

C. Kahoolawe island reserve operations center, Kahoolawe

Various improvements at:

Kuhela operations center $10,500,000

Honokanala road 1,000,000

Alternative energy facility 1,000,000

Maui information center 5,000,000

Total funding $17,500,000

D. Nahiku school community center, Maui

Plans, design, and construction for a pavilion to be built on the old Nahiku school grounds to serve as a community gathering facility where community members can meet to have social, cultural, and educational events. Facility to include restrooms.

Total funding $1,000,000

E. Hui Noeau visual arts center, Maui

Acquistion of land in Kaluanui to prevent displacement of Hui Noeau Visual Arts Center. $         

Repair existing buildings, driveway paving, and main house electrical upgrades. 240,000

Total funding $         

F. Palaau state park, Molokai

Plans, design, and construction of restroom facilities.

Total funding $1,000,000

5. To be expended by the county of Maui:

A. Cultural learning center, Molokai

Plans, design, and construction for a cultural learning center at Malama park and Palaau park and for visitor coordination centers.

Total funding $ 200,000

B. Molokai electric plant, Molokai

Plans, design, and construction to clean up the old Molokai electric plant, build a shared warehouse for new and existing business, and establish a business incubator and movie theatre.

Total funding $ 800,000

C. Emergency medical services, Maui

Emergency medical helicopter service.

Total funding $1,000,000

SECTION 2. The director of finance is authorized to issue general obligation bonds in the sum of $        , or so much thereof as may be necessary, for fiscal year 2006-2007, for the purpose of capital improvements in the thirteenth representative district.

SECTION 3. The appropriations made for the capital improvement projects authorized in this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all appropriations that are unencumbered as of June 30, 2008, shall lapse as of that date.

SECTION 4. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agencies for the purposes of this Act.

SECTION 5. This Act shall take effect on July 1, 2006.