Report Title:
CIP; Kapiolani Community College
Description:
Appropriates funding for capital improvement projects for the benefit of the Kapiolani Community College.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
3187 |
TWENTY-THIRD LEGISLATURE, 2006 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the kapiolani community college.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2006-2007:
A. Kapiolani community college, campus wide
Plans and design to refurbish termite damaged buildings, phase II.
Plans $23,000
Design $207,000
Total funding $230,000
B. Culinary cooking building
Design and construction to provide make-up air in ohia 109.
Design $64,350
Construction $364,650
Total funding $429,000
C. Campus wide
Design and construction to install energy management system.
Design $15,000
Construction $857,400
Total funding $872,400
D. Cafeteria building
Design and construction to replace and repair air conditioning chiller and air handlers.
Design $120,000
Construction $1,200,000
Total funding $1,320,000
E. Culinary building
Design and construction to re-roof.
Design $30,000
Construction $155,000
Total funding $185,000
F. Campus buildings
Design and construction to repair or replace Baltimore air conditioning cooling towers.
Design $49,500
Construction $214,800
Total funding $264,300
G. Culinary building
Design and construction to repair or replace air conditioning chiller and air handlers.
Design $120,000
Construction $1,200,000
Total funding $1,320,000
H. Culinary building
Design and construction to re-roof.
Design $29,614
Construction $167,810
Total funding $197,424
I. Performing arts building
Design and construction to renovate and add showers.
Design $25,000
Construction $100,000
Total funding $125,000
J. Chapel building
Design and construction to refurbish building.
Design $65,000
Construction $422,000
Total funding $487,000
K. Arts and sciences building
Design and construction to re-roof building to repair leaks.
Design $15,167
Construction $85,945
Total funding $101,112
L. Arts and sciences building
Design and construction to re-roof building to repair leaks.
Design $13,440
Construction $76,164
Total funding $89,604
M. Campus buildings
Design and construction to re-roof building to repair leaks.
Design $34,000
Construction $228,000
Total funding $262,000
N. Campus wide
Design and construction to upgrade electrical system.
Design $39,000
Construction $150,000
Total funding $189,000
O. New interior service road
Design and construction to connect Alani Child Care Center to Olopua building.
Design $30,000
Construction $200,000
Total funding $230,000
P. Service roads
Design and construction to resurface road fronting building 6937.
Design $29,000
Construction $98,000
Total funding $127,000
Q. Campus wide
Design and construction to refurbish or replace exterior light fixtures.
Design $70,500
Construction $480,000
Total funding $550,500
R. Parking lots
Design and construction to resurface.
Design $80,000
Construction $508,000
Total funding $588,000
S. Campus wide
Design and construction to resurface asphalt walkways and bike paths, including Alani building.
Design $28,500
Construction $190,000
Total funding $218,500
T. Culinary building and cafeteria building
Design and construction to renovate and refurbish food service public areas.
Design $40,500
Construction $177,672
Total funding $218,172
U. Culinary building and cafeteria building
Design and construction to replace fixed equipment and repair rooms.
Design $50,000
Construction $216,000
Total funding $266,000
V. Chapel building
Design and construction to repaint exterior of building.
Design $4,595
Construction $26,037
Total funding $30,632
W. Campus wide
Design and construction to re-key with electronic keying system.
Design $43,000
Construction $375,960
Total funding $418,960
X. Campus wide
Design and construction to upgrade and replace landscaping and irrigation system.
Design $47,000
Construction $429,000
Total funding $476,000
Provided that all construction work meet or exceed the leadership in energy and environmental design silver rating standards for new construction/major renovation work (LEED-NC) and existing building operations (LEED-EB) established by the United States Green Building Council for developing high-performance, sustainable buildings.
SECTION 2. The sums appropriated shall be expended by the University of Hawaii for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2006.
INTRODUCED BY: |
_____________________________ |