Report Title:

CIP; 31st District

Description:

Appropriates funds for capital improvement projects for the benefit of the thirty-first district.

HOUSE OF REPRESENTATIVES

H.B. NO.

3026

TWENTY-THIRD LEGISLATURE, 2006

 

STATE OF HAWAII

 


 

A BILL FOR AN ACT

 

relating to capital improvement projects for the benefit of the Thirty-first district.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2006-2007:

1. To be expended by the department of education:

A. Aliamanu elementary school, Oahu

Design and construction for acoustical tile installation and renovation of cafeteria.

Design $1,000

Construction $59,000

Total funding $60,000

B. Aliamanu elementary school, Oahu

Plans, design, and construction for office for clerical, administrative, and support staff.

Plans $1,000

Design $1,000

Construction $5,998,000

Total funding $6,000,000

C. Aliamanu elementary school, Oahu

Plans, design, and construction for a classroom building.

Plans $1,000

Design $1,000

Construction $1,498,000

Total funding $1,500,000

D. Aliamanu elementary school, Oahu

Plans, design, and construction for security fence/cattle gates.

Plans $1,000

Design $1,000

Construction $73,000

Total funding $75,000

E. Aliamanu elementary school, Oahu

Design and construction for electrical upgrades.

Design $1,000

Construction $499,000

Total funding $500,000

F. Aliamanu elementary school, Oahu

Design and construction for school media-library center.

Design $1,000

Construction $7,499,000

Total funding $7,500,000

G. Aliamanu middle school, Oahu

Plans, design, and construction for upgrade to electrical system.

Plans $1,000

Design $1,000

Construction $348,000

Total funding $350,000

H. Aliamanu middle school, Oahu

Plans, design, and construction to repair volleyball/basketball courts.

Plans $1,000

Design $1,000

Construction $238,000

Total funding $240,000

I. Moanalua elementary school, Oahu

Plans, design, and construction for eight classrooms to replace existing portable classrooms.

Plans $1,000

Design $1,000

Construction $3,998,000

Total funding $4,000,000

J. Moanalua elementary school, Oahu

Plans, design, and construction to expand library building for a technology center.

Plans $1,000

Design $1,000

Construction $298,000

Total funding $300,000

K. Moanalua elementary school, Oahu

Construction for a retaining wall along Moanalua stream for kindergarten playground and emergency repairs to correct hazardous and unsafe conditions.

Construction $450,000

Total funding $450,000

L. Moanalua high school, Oahu

Plans, design, and construction for a school performing arts center/auditorium.

Plans $1,000

Design $949,000

Construction $17,000,000

Total funding $17,950,000

M. Moanalua high school, Oahu

Design and construction for recrowning of the athletic field.

Design $1,000

Construction $449,000

Total funding $450,000

N. Moanalua middle school, Oahu

Plans, design, and construction for electrical upgrades for entire school campus phase II.

Plans $1,000

Design $1,000

Construction $148,000

Total funding $150,000

O. Moanalua middle school, Oahu

Plans, design, and construction for renovation of regular classrooms.

Plans $1,000

Design $1,000

Construction $248,000

Total funding $250,000

SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

SECTION 3. This Act shall take effect on July 1, 2006.

INTRODUCED BY:

_____________________________