Report Title:

CIP; 37th Representative District

Description:

Appropriates funds for capital improvement projects in the 37th representative district.

HOUSE OF REPRESENTATIVES

H.B. NO.

2249

TWENTY-THIRD LEGISLATURE, 2006

 

STATE OF HAWAII

 


 

A BILL FOR AN ACT

 

MAKING AN APPROPRIATION FOR THE thirty-seventh representative DISTRICT.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $11,186,600, or so much thereof as may be necessary, for fiscal year 2006-2007, for the following capital improvements in the thirty-seventh representative district:

1. Schools

A. Kanoelani Elementary School

Installation of air conditioning of 7 classrooms in P Building and the administration building.

Equipment $ 88,000

Installation  88,000

Total $176,000

B. Mililani Uka Elementary School

Installation of air conditioning for a portion of the administration building.

Equipment $ 26,400

Installation 19,800

Materials    4,400

Total $ 50,600

C. Mililani High School

Additional construction money for 10-classroom building.

Construction $1,200,000

Equipment and appurtenances   300,000

Total $1,500,000

Purchase of new phone system. $80,000

D. Mililani Middle School

Design and construction of covered playcourts.

Design $    1,000

Construction  2,199,000

Total $2,200,000

Design and construction of covered bus stop and benches.

Design $10,000

Construction  75,000

Total $85,000

E. Kipapa Elementary School

Plans, design, and construction to update school's electrical system.

Plans $    1,000

Design 1,000

Construction 1,198,000

Total $1,200,000

Plans, design, and construction of parking lot.

Plans $    1,000

Design 1,000

Construction 2,498,000

Total $2,500,000

F. Mililani Waena Elementary School

Design and construction of renovation of pod-type classrooms to be converted into four single classrooms.

Design $ 60,000

Construction  510,000

Total $570,000

Design and construction of ventilation system for food preparation area.

Design $ 30,000

Construction  145,000

Total $175,000

G. Pearl City High School

Connect auditorium to school water source.

Study $ 30,000

Plans 20,000

Design  30,000

Construction  250,000

Total $330,000

H. Mililani Ike Elementary School

Procurement and installation of 8 portable classrooms. $1,920,000

Design and construction of portable restroom adjacent to portable classrooms.

Design $ 50,000

Construction  350,000

Total $400,000

SECTION 2. The appropriations made for the capital improvement projects authorized in this Act, shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all appropriations which are unencumbered as of June 30, 2008, shall lapse as of that date.

SECTION 3. The sum appropriated for the capital improvement projects set forth in section 1 shall be expended by the department of accounting and general services for the purposes of this Act.

SECTION 4. This Act shall take effect on July 1, 2006.

INTRODUCED BY:

_____________________________