Report Title:
CIP; 48th Representative District
Description:
Appropriate funds for capital improvement projects for the benefit of the 48th representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1894 |
TWENTY-THIRD LEGISLATURE, 2006 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the forty-eighth representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2006-2007.
1. To be expended by the University of Hawaii:
A. Windward community college, Oahu
Plans, design, construction, and equipment for a new library; ground and site improvements; and equipment and appurtenances.
Plans $1,000
Design $1,799,000
Construction $23,410,000
Equipment $2,515,000
Total funding $27,725,000
2. To be expended by the department of education:
A. James B. Castle high school, Oahu
Design, construction, and equipment to expand the cafeteria dining room for additional student dining; ground and site improvements; equipment and appurtenances.
Design $300,000
Construction $2,600,000
Equipment $200,000
Total funding $3,100,000
B. James B. Castle high school, Oahu
Design, construction, and equipment for the installation of an all-weather track field; site and ground improvements; equipment and appurtenances.
Design $30,000
Construction $700,000
Equipment $20,000
Total funding $750,000
C. Heeia elementary school, Oahu
Design and construction for the expansion of the parking lot; ground and site improvements; and equipment and appurtenances.
Design $30,000
Construction $150,000
Total funding $180,000
D. Heeia elementary school, Oahu
Design and construction for improvements and upgrade of the electrical system; ground and site improvements; equipment and appurtenances.
Design $50,000
Construction $500,000
Total funding $550,000
E. Kaneohe elementary school, Oahu
Design and construction for the expansion of the parking lot; ground and site improvements; equipment and appurtenances.
Design $30,000
Construction $150,000
Total funding $180,000
F. Kapunahala elementary school, Oahu
Design, construction, and equipment for the renovation of the parent community network center room; replacement and expansion of the air conditioning equipment in building E; ground and site improvements; equipment and appurtenances.
Design $20,000
Construction $175,000
Equipment $125,000
Total funding $320,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2006.
INTRODUCED BY: |
_____________________________ |