Report Title:
CIP; 6th Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 6th representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1319 |
TWENTY-THIRD LEGISLATURE, 2005 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE SIXTH REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2005-2006:
1. To be expended by the county of Hawaii:
A. Laaloa avenue, Lako street, and Kealakehe parkway, Hawaii.
Plans, design, and construction for improvements to and completion of mauka-makai connectors.
Plans $1,000
Design $1,000
Construction $4,998,000
Total funding $5,000,000
2. To be expended by the University of Hawaii:
A. University of Hawaii – west Hawaii campus, Hawaii
Design, construction, and equipment for the initial administrative headquarters of an extension to the University of Hawaii at Manoa.
Design $1,000
Construction $2,498,000
Equipment $1,000
Total funding $2,500,000
3. To be expended by the department of accounting and general services:
A. Alii parkway, Hawaii
Plans, design, and construction for an avenue to resolve the current archaeologic impasse between Hokulia and Protect Keopuka Ohana.
Plans $50,000
Design $50,000
Construction $900,000
Total funding $1,000,000
B. Kona drug treatment center, Hawaii
Plans, design, construction, and equipment for an inpatient primary drug treatment center in Kailua-Kona.
Plans $25,000
Design $25,000
Construction $900,000
Equipment $50,000
Total funding $1,000,000
C. Kona homeless shelter, Hawaii
Design, construction, and equipment for an addition to the shelter to accommodate overnight staff.
Design $1,000
Construction $248,000
Equipment $1,000
Total funding $250,000
D. Kona volleyball center, Hawaii
Plans, design, construction, and equipment for a volleyball facility at the old Kona airport.
Plans $15,000
Design $35,000
Construction $175,000
Equipment $25,000
Total funding $250,000
E. Old Kona airport fitness center, Hawaii
Plans, design, construction, and equipment for a fitness center in Kailua-Kona, with special use privileges for West Hawaii's middle school- and high school-age athletes.
Plans $50,000
Design $50,000
Construction $250,000
Equipment $100,000
Total funding $450,000
F. West Hawaii community health center, Hawaii
Design, construction, and equipment for a comprehensive community health center in Kailua-Kona to provide primary healthcare, mental healthcare, and early intervention substance abuse care.
Design $1,000
Construction $748,000
Equipment $1,000
Total funding $750,000
G. Holualoa elementary school, Hawaii
Plans, design, and construction for cesspool system
removal.
Plans $1,000
Design $1,000
Construction $178,000
Total funding $180,000
H. Holualoa elementary school, Hawaii
Plans, design, and construction for telecommunications
upgrade.
Plans $1,000
Design $1,000
Construction $298,000
Total funding $300,000
I. Holualoa elementary school, Hawaii
Plans, design, and construction for ramp installation
from room five and room six.
Plans $1,000
Design $1,000
Construction $10,000
Total funding $12,000
J. Holualoa elementary school, Hawaii
Plans, design, and construction for ADA transition
accessibility.
Plans $1,000
Design $1,000
Construction $248,000
Total funding $250,000
K. Holualoa elementary school, Hawaii
Plans, design, and construction for an air conditioning system.
Plans $1,000
Design $1,000
Construction $3,498,000
Total funding $3,500,000
L. Holualoa elementary school, Hawaii
Plans, design, and construction for administrative/
library building renovation.
Plans $1,000
Design $1,000
Construction $10,659,000
Total funding $10,661,000
M. Holualoa elementary school, Hawaii
Plans, design, and construction for a six-classroom
building replacement.
Plans $1,000
Design $1,000
Construction $4,498,000
Total funding $4,500,000
N. Kahakai elementary school, Hawaii
Plans, design, and construction for cesspool removal.
Plans $1,000
Design $1,000
Construction $348,000
Total funding $350,000
O. Kahakai elementary school, Hawaii
Plans, design, construction, and equipment for school
air conditioning system.
Plans $1,000
Design $1,000
Construction $3,497,000
Equipment $1,000
Total funding $3,500,000
P. Kahakai elementary school, Hawaii
Plans, design, and construction for architectural
barrier removal.
Plans $1,000
Design $1,000
Construction $490,000
Total funding $492,000
Q. Kealakehe elementary school, Hawaii
Plans, design, and construction for renovation of
administrative/library building.
Plans $1,000
Design $1,000
Construction $11,933,000
Total funding $11,935,000
R. Kealakehe elementary school, Hawaii
Plans, design, and construction for playfield and
retention basin.
Plans $1,000
Design $1,000
Construction $2,498,000
Total funding $2,500,000
S. Kealakehe elementary school, Hawaii
Plans, design, and construction for a six-classroom
building.
Plans $1,000
Design $1,000
Construction $2,998,000
Total funding $3,000,000
T. Kealakehe elementary school, Hawaii
Plans, design, and construction for cesspool system
removal.
Plans $1,000
Design $1,000
Construction $498,000
Total funding $500,000
U. Kealakehe elementary school, Hawaii
Plans, design, and construction for an air
conditioning system.
Plans $1,000
Design $1,000
Construction $3,498,000
Total funding $3,500,000
V. Kealakehe II elementary school, Hawaii
Plans, design, and construction for a new school.
Plans $1,000
Design $1,000
Construction $24,998,000
Total funding $25,000,000
W. Kealakehe high school, Hawaii
Plans, design, and construction for an eight-classroom
building.
Plans $1,000
Design $1,000
Construction $3,998,000
Total funding $4,000,000
X. Kealakehe high school, Hawaii
Plans, design, and construction for an air
conditioning system.
Plans $1,000
Design $1,000
Construction $9,998,000
Total funding $10,000,000
Y. Kealakehe intermediate school, Hawaii
Plans, design, and construction for an eight-classroom
building.
Plans $1,000
Design $1,000
Construction $9,558,000
Total funding $9,560,000
Z. Kealakehe intermediate school, Hawaii
Plans, design, and construction for renovation of
administration/library building.
Plans $1,000
Design $1,000
Construction $6,778,000
Total funding $6,780,000
AA. Kealakehe intermediate school, Hawaii
Plans, design, and construction for cesspool system
removal.
Plans $1,000
Design $1,000
Construction $348,000
Total funding $350,000
BB. Kealakehe intermediate school, Hawaii
Plans, design, and construction for SPED trailer.
Plans $1,000
Design $1,000
Construction $498,000
Total funding $500,000
CC. Kealakehe intermediate school, Hawaii
Plans, design, and construction for air conditioning
system.
Plans $1,000
Design $1,000
Construction $3,998,000
Total funding $4,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agencies for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2005.