Report Title:
CIP; 40th Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 40th representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
807 |
TWENTY-FIRST LEGISLATURE, 2001 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the fortieth representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenue of the State of Hawaii for the fiscal year 2000-2001:
1. To be expended by the department of accounting and general services:
A. Kaala elementary school, Oahu
Construction for electrical upgrade to support additional equipment and classroom lighting.
Equipment $1,000
Construction $103,000
Total funding $104,000
B. Kaala elementary school, Oahu
Design, construction, and equipment to install air conditioning in the library and computer center.
Design $10,300
Construction $257,500
Equipment $206,000
Total funding $473,800
C. Helemano elementary school, Oahu
Design, construction, and equipment for a library.
Design $200,000
Construction $2,235,000
Equipment $50,000
Total funding $2,235,000
D. Iliahi elementary school, Oahu
Construction to install air conditioning, new mechanical room, windows, doors and a bell in the library.
Construction $210,000
Total funding $210,000
E. Wahiawa elementary school, Oahu
Design and construction for a new cafeteria kitchen floor.
Design $25,000
Construction $65,000
Total funding $90,000
F. Wahiawa elementary school, Oahu
Design and construction to repaint the exterior and resurface the walkways of buildings C, D, E, G, H, and the cafeteria as well as the interior of the cafeteria.
Design $25,000
Construction $36,000
Total funding $61,000
G. Wahiawa middle school, Oahu
Design and construction to resurface the playcourt.
Design $25,000
Construction $575,000
Total funding $600,000
H. Wahiawa middle school, Oahu
Design and construction to landscape vacant lot, clean, grade, plant, and enclose the area.
Design $25,000
Construction $175,000
Total funding $200,000
I. Leilehua high school, Oahu
Design, construction, and equipment to convert the old administration building into a counseling and "one stop" center.
Design $25,000
Construction $225,000
Equipment $1,000
Total funding $256,000
J. Leilehua high school, Oahu
Design, construction and equipment to convert room fifty-three into a technology center.
Design $25,000
Construction $225,000
Equipment $1,000
Total funding $256,000
SECTION 2. The sums appropriated for the respective capital projects set forth in Section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2001.
INTRODUCED BY: |
_____________________________ |