Report Title:
CIP; 42nd Representative District
Description:
Appropriation for capital improvement projects for the benefit of the 42nd representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1490 |
TWENTY-FIRST LEGISLATURE, 2001 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE FORTY-SECOND REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2000-2001.
I. To be expended by the department of accounting and general services:
A. Kapolei Public Library, Oahu, Hawaii
1. Plan, design, construction and equipment of Phase II addition to the library.
Plan, design, construction, $12,000,000
Total funding 12,000,000
2. Supply books and staffing for Phase I of library
Books and staffing 2,000,000
Total funding 2,000,000
B. Kapolei High School, Oahu, Hawaii
1. Construction and equipment for first and/or second increment. Ground and site improvements, equipment and appurtenances. To relieve Campbell High School and phase in of additional grades to the school. The school will accommodate additional enrollment growth due to housing developments on the Ewa plains.
Construction and equipment 22,000,000
2. Construction and equipment for second increment, Phase II. Ground and site improvements, equipment and appurtenances. To relieve Campbell High School and accommodate enrollment increases due to growth of housing in the Villages of Kapolei and on the Ewa plains.
Construction and equipment 22,000,000
3. Design and construction of auditorium for joint school and community usage.
Design and construction 22,000,000
Total funding 66,000,000
C. Kaleiopuu Elementary School, Oahu, Hawaii
1. Design and construction of an alternate emergency exit with ramp at rear of school for safety.
Design 50,000
Construction 150,000
Total funding 200,000
2. Design and construct concrete firebreak at rear of school for safety.
Design 50,000
Construction 125,000
Total funding 175,000
3. Redesign and construct a rescue area in Building "G" to correct design flaw which cuts off access to stairwell for safety.
Design 50,000
Construction 75,000
Total funding 125,000
4. Design and construct a retaining wall pn the entire mauka side of the school campus for safety.
Design 30,000
Construction 75,000
Total funding 105,000
5. Design and construct mauka side extension to fire lane for access to the rear of campus for safety.
Design 25,000
Construction 50,000
Total funding 75,000
6. Design, construct, and install grease trap for cafeteria kitchen basin for compliance with Health and EPA.
Design 1,000
Construction 15,000
Equipment 5,000
Total funding 21,000
7. Design and install retractable awning in lieu of air-conditioning on the Waianae side of Building A.
Design 1,000
Construction 5,000
Equipment 25,000
Total funding 31,000
D. Kapolei Elementary School, Oahu, Hawaii
1. Design and construction of 2 traffic lights and 2 flashing lights at the corner of Kamaaha Avenue and the intersection of Kumu Iki Street and Kamaaha Loop.
Design 50,000
Construction 250,000
Total funding 300,000
2. Remove and replace sidewalk fronting Building 5 to Building 8 to comply with ADA requirements.
Design 5,000
Construction 10,000
Total funding 15,000
3. Repaint buildings D, E, and F.
Cost 25,000
Total funding 25,000
E. Ewa Elementary School, Oahu, Hawaii
1. Design and construct a sixteen-classroom building, ground and site improvements, equipment and appurtenances.
Design 120,000
Construction 1,650,000
Equipment 100,000
Total funding 1,870,000
2. Design and upgrade electrical system for Buildings C and D
Design 10,000
Construction 100,000
Total funding 110,000
3. Design and construct chain link fence fronting school plant.
Design 1,000
Construction 10,000
Total funding 11,000
4. Design and construct replacement for glass windows in Building L
Design 30,000
Construction, renovation 200,000
Total funding 230,000
F. Makakilo Elementary School, Oahu, Hawaii
1. Renovation and upgrade of electrical and wiring infrastructure for entire school plant.
Design 50,000
Construction 250,000
Total funding 300,000
2. Install air conditioning for entire school plant.
Design 50,000
Construction 500,000
Total funding 550,000
3. Design and install new night lighting fixtures in entire school plant for safety.
Design 50,000
Construction 150,000
Total funding 200,000
4. Design and construct new parking paved parking area in rear of school plant
Design 10,000
Construction 90,000
Total funding 100,000
5. Design and construct walkway and safety rails between Buildings H and C.
Design 5,000
Construction 30,000
Total funding 35,000
6. Design and install water sprinkler system for entire school plant.
Design 5,000
Construction 25,000
Total funding 30,000
G. Mauka Lani Elementary School, Oahu, Hawaii
1. Design and construct central air-conditioning for Building A (16 classrooms).
Design 100,000
Construction 700,000
Total funding 800,000
2. Design and install air-conditioning for 17 portable classrooms.
Design 50,000
Construction 200,000
Total funding 250,000
3. Design and construct retaining walls with drainage and landscaping for portion above the upper and behind school plant.
Design 75,000
Construction 325,000
Total funding 400,000
4. Design and construct school perimeter fencing for entire school plant.
Design 15,000
Construction 335,000
Total funding 350,000
5. Planning, design, and site location for possible annex complex or building to new school campus.
Planning 100,000
Design 250,000
Total funding 350,000
H. Royal Kunia Elementary School, Oahu, Hawaii
Construct the first increment, ground and site improvements, equipment and appurtenances, necessary to relieve Kalaiopu'u elementary school and address enrollment growth in the community.
Design 1,000,000
Construction 7,500,000
Equipment 100,000
Total funding 8,600,000
I. Barbers Point Elementary School, Oahu, Hawaii
1. Design and install air-conditioning for school library, ground and site improvements, equipment and appurtenances.
Design 33,000
Construction 273,000
Equipment 1,000
Total funding 307,000
2. Design and install central air-conditioning for classrooms and administrative facilities in Buildings B, C, D, E, F, G, H, and I.
Design 50,000
Construction 650,000
Total funding 700,000
3. Design and install rubberized surfacing beneath five newly installed playground equipments.
Design 5,000
Construction 85,000
Total funding 90,000
4. Design and construct access pathway from Building F to grade K playground equipment.
Design 1,000
Construction 14,000
Total funding 15,000
5. Design and install sprinkler and irrigation system for entire campus.
Design 5,000
Construction 20,000
Total funding 25,000
6. Design and construct repaving and resurfacing of driveway and parking area fronting cafeteria and administration building.
Design 5,000
Construction 50,000
Total funding 55,000
7. Design and construct the repaving and surfacing on basketball court.
Design 1,000
Construction 18,000
Total funding 19,000
8. Design and construct paved parking area along Tulagi and Cophaee Streets
Design 10,000
Construction 75,000
Total funding 85,000
J. Campbell High School, Oahu, Hawaii
1. Design and construct central air-conditioning system for entire school plant.
Design 150,000
Construction 800,000
Total funding 950,000
2. Plan and design Transition Center
Design 25,000
Total funding 25,000
3. Plan and design International Media Technology Academy
Design 50,000
Total funding 50,000
K. Ilima Intermediate School, Oahu, Hawaii
1. Design and construct sprinkler system for entire school plant.
Design 5,000
Construction 25,000
Total funding 30,000
2. Design and construct renovation of administration building.
Design 5,000
Construction 25,000
Total funding 30,000
3. Design and repaint exterior and interior of entire school plant.
Design 10,000
Construction 50,000
Total funding 60,000
L. Waipahu Intermediate School, Oahu, Hawaii
1. Design and construct new cafeteria facility, renovate temporary facilities for two classrooms, ground and site improvements, equipment and appurtenances as existing facilities are substandard and the classrooms are required to accommodate shortages.
Design 270,000
Construction 2,600,000
Equipment 125,000
Total funding 2,995,000
2. Design and construct an eight-classroom building.
Design 100,000
Construction 1,700,000
Equipment 300,000
Total funding 2,100,000
M. Waipahu High School, Oahu, Hawaii
1. Design and construct stadium bleachers, press box and concession stand.
DESIGN $100,000
CONSTRUCTION $900,000
TOTAL $1,000,000
2. Design and construct lighting for stadium complex and to parking areas for safety.
DESIGN $75,000
CONSTRUCTION $200,000
TOTAL FUNDING $275,000
3. Design and construct building with eight classrooms; ground and site improvements, equipment and appurtenances. Required to address actual and projected enrollment increases.
DESIGN $320,000
CONSTRUCTION $3,100,000
EQUIPMENT $100,000
TOTAL FUNDING $3,520,000
N. KAPOLEI CIVIC CENTER
1. Kapolei civic center parking structure, Oahu
DESIGN $670,000
TOTAL FUNDING $670,000
II. To be expended by the department of transportation:
A. KALAELOA AIRPORT IMPROVEMENTS, OAHU
Construction for airport improvements including striping, airfield lighting, and navigational aids. This project is deemed necessary to qualify for federal aid financing and/or reimbursement.
CONSTRUCTION $4,330,000
TOTAL FUNDING $4,330,000
B. GANTRY CRANE, KALAELOA BARBERS POINT HARBOR, OAHU
Design and construction for the installation of a cargo container gantry crane, a crane rail system, and other related improvements.
DESIGN $400,000
CONSTRUCTION $4,400,000
TOTAL FUNDING $4,800,000
C. FORT BARRETTE ROAD WIDENING, FARRINGTON HIGHWAY TO BARBERS POINT GATE, OAHU
Plans for widening the exiting roadway to four lanes and other improvements, including right and left turning lanes, sidewalks, bikeway, highway lighting, drainage, traffic signals, landscaping and other improvements.
PLANS $400,000
TOTAL FUNDING $400,000
D. TRAFFIC SIGNALS AT Honowai Street and Kunia Road, Oahu
DESIGN $50,000
CONSTRUCTION $500,000
TOTAL FUNDING $550,000
E. H-1 Makakilo Interchange: New west-bound on-ramp, Oahu
PLANS $150,000
TOTAL FUNDING $150,000
F. H-1 Kapolei Interchange: New Interchange
PLANS $300,000
TOTAL FUNDING $300,000
G. H-1 Palailai Interchange Improvements
PLANS $100,000
TOTAL FUNDING $100,000
H. H-1 North-South Interchange
PLANS $300,000
TOTAL FUNDING $300,000
I. Farrington Highway: Highway widening from Kalaeloa to Kamokila
PLANS $200,000
TOTAL FUNDING $200,000
J. Farrington Highway: Highway widening from Kapolei Golf Course to Fort Weaver Road.
PLANS $350,000
TOTAL FUNDING $350,000
K. Farrington Highway Makaiwa Hills interchange.
PLANS $200,000
TOTAL FUNDING $200,000
L. Fort Barrette Road widening: Farrington Highway to FD Roosevelt Blvd.
PLANS $300,000
TOTAL FUNDING $300,000
M. Fort Weaver Road Widening: Farrington Highway to Geiger Road.
PLANS $250,000
TOTAL FUNDING $250,000.
N. Kalaeloa roadway improvements.
DESIGN $150,000
TOTAL FUNDING $150,000
O. Kalaeloa Blvd. Corridor improvements.
PLANS $200,000
TOTAL FUNDING $200,000
P. Kapolei Parkway: New road North-South Road to Papipi Road.
DESIGN $250,000
TOTAL FUNDING $250,000
Q. Makakilo Drive extension for second access road.
PLANS $200,000
TOTAL FUNDING $200,000
R. New Mauka frontage road between Makakilo Drive to Kalaeloa Blvd.
PLANS $150,000
TOTAL FUNDING $150,000
S. New Kapolei collector: Farrington Highway to Fort Weaver Road.
PLANS $300,000
TOTAL FUNDING $300,000
T. North-South Road development: Kapolei Parkway to H-1.
PLANS $350,000
TOTAL FUNDING $350,000
U. LEEWARD COMMUNITY COLLEGE, SECOND ACCESS, OAHU
Plans for a second access to the Leeward Community College.
PLANS $500,000
TOTAL FUNDING $500,000
III. To be expended by the department of business, economic development & tourism:
A. KALAELOA HOMELESS SHELTER, IMPROVEMENTS TO FACILITIES FOR THE HOMELESS
Design, construction and equipment for the renovation of two barracks at former Barbers Point Naval Air Station that are slated for use as homeless shelters in 2001. One 70-unit building for homeless mentally ill singles and one 44-unit building for homeless families. The CIP request will provide water meters/services, equipment, two vehicles, and some structural and landscaping improvements.
DESIGN $4,000
CONSTRUCTION $298,000
EQUIPMENT $118,000
TOTAL FUNDING $420,000
IV To be expended by the judiciary:
KAPOLEI JUDICIARY COMPLEX, OAHU
Construction for the Kapolei Judiciary Complex.
CONSTRUCTION $69,900,000
TOTAL FUNDING $69,900,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. The appropriations made for capital improvement projects authorized in this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all appropriations which are unencumbered as June 30, 2003, shall lapse as of that date.
SECTION 4. This Act shall take effect on July 1, 2001.