REPORT TITLE:
9th Senatorial District CIP


DESCRIPTION:
Authorizes issuance of GO bonds and appropriates funds for
capital improvement projects of the 9th Senatorial District.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                             
THE SENATE                              S.B. NO.           1590
TWENTIETH LEGISLATURE, 1999                                     
STATE OF HAWAII                                                 
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

AUTHORIZING THE ISSUANCE OF GENERAL OBLIGATION BONDS AND MAKING
   AN APPROPRIATION FOR CAPITAL IMPROVEMENT PROJECTS OF THE
   NINTH SENATORIAL DISTRICT.



BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The director of finance is authorized to issue
 
 2 general obligation bonds in the sum of $7,244,000, and the same
 
 3 sum, or so much thereof as may be necessary is appropriated out
 
 4 of the general obligation bond fund of the State of Hawaii for
 
 5 the following projects:
 
 6 1.   To be expended by the department of accounting and general
 
 7 services:
 
 8      A.   KAIMUKI MIDDLE SCHOOL, OAHU
 
 9           Renovation and upgrade of computer lab and wiring.
 
10           Plans                                            $1,000
 
11           Design                                           $5,000
 
12           Construction                                    $39,000
 
13           Equipment                                       $55,000
 
14                     TOTAL FUNDING                        $100,000
 
15      B.   KAIMUKI HIGH SCHOOL, OAHU
 
16           Construction of a parking lot adjacent to the gym.
 
17           Plans                                                  
 
18           Design                                                 
 

 
Page 2                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1           Construction                                           
 
 2                     TOTAL FUNDING                        $500,000
 
 3      C.   KAIMUKI HIGH SCHOOL, OAHU
 
 4           Renovation and improvement to buildings G and F to
 
 5           accommodate updated curricula and instruction.
 
 6           Plans                                                  
 
 7           Design                                                 
 
 8           Construction                                           
 
 9                     TOTAL FUNDING                        $500,000
 
10      D.   KAIMUKI HIGH SCHOOL, OAHU
 
11           Relocating and reinstalling of air conditioning units
 
12           from the library rooftop to a ground level location,
 
13           reroofing affected library rooftop areas, reconfiguring
 
14           air ducts, and replacing damaged ceiling tiles of the
 
15           Kaimuki high school library.
 
16           Plans                                                  
 
17           Design                                                 
 
18           Construction                                           
 
19                     TOTAL FUNDING                      $1,000,000
 
20      E.   HOKULANI ELEMENTARY SCHOOL, OAHU
 
21           Purchasing and installing safe groundcover for the
 
22           kindergarten playground facility at Hokulani elementary
 
23           school.
 

 
Page 3                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1           Plans                                                  
 
 2           Design                                                 
 
 3           Construction                                           
 
 4                     TOTAL FUNDING                         $20,000
 
 5      F.   JOHN H. WILSON ELEMENTARY SCHOOL, OAHU
 
 6           Cool storage air conditioning system in classrooms.
 
 7           Plans                                           $24,000
 
 8           Design                                          $39,000
 
 9           Construction                                   $176,000
 
10                     TOTAL FUNDING                        $239,000
 
11      G.   JOHN H. WILSON ELEMENTARY SCHOOL, OAHU
 
12           Telecommunications and power improvements.
 
13           Plans                                           $15,000
 
14           Design                                          $22,500
 
15           Construction                                   $112,500
 
16                     TOTAL FUNDING                        $150,000
 
17      H.   KALANI HIGH SCHOOL, OAHU
 
18           Extension of the cafeteria to include but not limited
 
19           to stage and backstage area for band and drama
 
20           performances.  Installation of additional electrical
 
21           sources for sound equipment and lighting.
 
22           Plans                                          $100,000
 
23           Design                                         $150,000
 

 
Page 4                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1           Construction                                   $750,000
 
 2                     TOTAL FUNDING                      $1,000,000
 
 3      I.   KALANI HIGH SCHOOL, OAHU
 
 4           Extension of administration building and library.
 
 5           Plans                                          $100,000
 
 6           Design                                         $150,000
 
 7           Construction                                   $750,000
 
 8                     TOTAL FUNDING                      $1,000,000
 
 9      J.   KALANI HIGH SCHOOL, OAHU
 
10           Increasing electrical load capacity for computers and
 
11           electronic equipment.
 
12           Plans                                           $50,000
 
13           Design                                          $75,000
 
14           Construction                                   $375,000
 
15                     TOTAL FUNDING                        $500,000
 
16      K.   KAHALA ELEMENTARY SCHOOL, OAHU
 
17           Increasing electrical load capacity for computers and
 
18           electronic equipment.
 
19           Plans                                           $15,000
 
20           Design                                          $22,500
 
21           Construction                                   $112,500
 
22                     TOTAL FUNDING                        $150,000
 

 
 
 
Page 5                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1      L.   WAIALAE ELEMENTARY SCHOOL, OAHU                        
 
 2           Increasing electrical load capacity for computers and
 
 3           electronic equipment.
 
 4           Plans                                           $15,000
 
 5           Design                                          $22,500
 
 6           Construction                                   $112,500
 
 7                     TOTAL FUNDING                        $150,000
 
 8      M.   LILI'UOKALANI ELEMENTARY SCHOOL, OAHU
 
 9           Increasing electrical load capacity for computers and
 
10           electronic equipment.
 
11           Plans                                           $15,000
 
12           Design                                          $22,500
 
13           Construction                                   $112,500
 
14                     TOTAL FUNDING                        $150,000
 
15      N.   KAPIOLANI COMMUNITY COLLEGE, OAHU
 
16           Minor CIP and renovation of classrooms, offices,
 
17           laboratories, and other related spaces.
 
18           Design                                         $100,000
 
19           Construction                                   $800,000
 
20           Equipment                                      $100,000
 
21                     TOTAL FUNDING                      $1,000,000
 
22      O.   OLD KAIMUKI LIBRARY, OAHU
 
23           Renovation and equipment to convert the former Kaimuki
 
24           library into a senior center.
 

 
Page 6                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1           Plans                                           $40,000
 
 2           Design                                          $60,000
 
 3           Construction                                   $400,000
 
 4           Equipment                                       $50,000
 
 5                     TOTAL FUNDING                        $550,000
 
 6 2.   To be expended by the department of transportation:
 
 7      A.   Traffic signals at Kalanianaole highway and Analii
 
 8           street, Oahu
 
 9           Install traffic signals at the intersection of
 
10           Kalanianaole highway and Analii street.
 
11           Plans                                            $1,000
 
12           Design                                           $4,000
 
13           Construction                                    $50,000
 
14                     TOTAL FUNDING                         $55,000
 
15 3.   To be expended by the city and county of Honolulu:
 
16      A.   Palolo medical clinic, Oahu.
 
17           Plans and                                              
 
18           Design                                          $40,000
 
19           Construction                                   $140,000
 
20                     TOTAL FUNDING                        $180,000
 
21      SECTION 2.  The sums appropriated for the respective capital
 
22 improvement projects set forth in section 1 shall be expended by
 
23 the designated expending agency for the purposes of this Act.
 

 
Page 7                                                     
                                     S.B. NO.           1590
                                                        
                                                        

 
 1      SECTION 3.  This Act shall take effect on July 1, 1999.
 
 2 
 
 3                           INTRODUCED BY:  _______________________