REPORT TITLE:
CIP for the 22nd district


DESCRIPTION:
CIP for the 22nd Representative District.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                        
HOUSE OF REPRESENTATIVES                H.B. NO.1584       
TWENTIETH LEGISLATURE, 1999                                
STATE OF HAWAII                                            
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE
   TWENTY-SECOND REPRESENTATIVE DISTRICT.


BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The following sums, or so much thereof as shall
 
 2 be sufficient to finance the projects listed in this Act, are
 
 3 hereby appropriated out of the general revenues of the State of
 
 4 Hawaii for fiscal year 1999-2000.
 
 5      A.   McKinley high school, Oahu
 
 6           Design and construction to complete the final phase of
 
 7           the school's technology plan, including the electrical
 
 8           upgrade of building F and video accessibility for the
 
 9           entire campus.
 
10           Design                                         $ 20,000
 
11           Construction                                    180,000
 
12           Total funding                                   200,000
 
13      B.   McKinley high school, Oahu
 
14           Design and construction to replace 800 to 1,000 boys
 
15           physical education lockers.
 
16           Design                                         $  5,000
 
17           Construction                                    195,000
 
18           Total funding                                   200,000
 

 
Page 2                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1      C.   McKinley high school, Oahu
 
 2           Design and construction to install four air
 
 3           conditioning units for building M.
 
 4           Design                                         $ 20,000
 
 5           Construction                                    180,000
 
 6           Total funding                                   200,000
 
 7      D.   McKinley high school, Oahu
 
 8           Design and construction to extend the student dining
 
 9           room to accommodate 1,200 to 1,500 students.
 
10           Design                                         $ 75,000
 
11           Construction                                    600,000
 
12           Total funding                                   675,000
 
13      E.   McKinley high school, Oahu
 
14           Design and construction to remove and replace all
 
15           windows in historic building W.
 
16           Design                                       $   10,000
 
17           Construction                                  4,990,000
 
18           Total funding                                 5,000,000
 
19      F.   McKinley high school, Oahu
 
20           Construction to resurface the areas between the
 
21           gymnasium and the boys physical education lockers.
 
22           Construction                                    $50,000
 
23           Total funding                                    50,000
 

 
Page 3                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1      G.   McKinley high school, Oahu
 
 2           Construction to resurface the areas between the
 
 3           cafeteria and auditorium.
 
 4           Construction                                    $40,000
 
 5           Total funding                                    40,000
 
 6      H.   Kaimuki high school, Oahu
 
 7           Design and construction to relocate six air
 
 8           conditioning units on the roof library to one large
 
 9           unit on the ground, re-roof sections affected, re-roof
 
10           ducts, and re-do ceiling tiles.
 
11           Design                                       $  150,000
 
12           Construction                                    850,000
 
13           Total funding                                 1,000,000
 
14      I.   Kaimuki high school, Oahu
 
15           Design and construction for a paved parking lot
 
16           adjacent to building O (gymnasium), ground and site
 
17           improvements, equipment, and appurtenances.
 
18           Design                                         $ 25,000
 
19           Construction                                    190,000
 
20           Total funding                                   215,000
 
21      J.   Kaimuki high school, Oahu
 
22           Design, construction, and equipment to renovate
 
23           building G (science/laboratories), equipment, and
 
24           appurtenances.
 

 
Page 4                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1           Design                                         $100,000
 
 2           Construction                                    450,000
 
 3           Equipment                                        50,000
 
 4           Total funding                                   600,000
 
 5      K.   Kaimuki high school, Oahu
 
 6           Design, construction, and equipment to renovate
 
 7           building F (home economic/art classrooms), equipment,
 
 8           and appurtenances.
 
 9           Design                                         $ 80,000
 
10           Construction                                    270,000
 
11           Equipment                                       100,000
 
12           Total funding                                   450,000
 
13      L.   Washington middle school, Oahu
 
14           Design and construction to install an automatic water
 
15           sprinkler system at the physical education playfield.
 
16           Design                                         $ 50,000
 
17           Construction                                    200,000
 
18           Total funding                                   250,000
 
19      M.   Kuhio elementary school, Oahu
 
20           Design and construction of a second floor to connect
 
21           the administration and library buildings.
 
22           Design                                         $105,000
 
23           Construction                                    595,000
 
24           Total funding                                   700,000
 

 
Page 5                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1      N.   McCully-Moiliili public library, Oahu
 
 2           Plans, design, and construction to install a pedestrian
 
 3           ramp from the Makahiki street exit to the city and
 
 4           county sidewalk.
 
 5           Plans                                           $ 1,000
 
 6           Design                                            1,000
 
 7           Construction                                      8,000
 
 8           Total funding                                    10,000
 
 9      O.   McCully-Moiliili public library, Oahu
 
10           Design, construction, and equipment to demolish and
 
11           replace a thirty-year-old concrete bicycle rack.
 
12           Design                                           $1,000
 
13           Construction                                      4,000
 
14           Equipment                                         1,000
 
15           Total funding                                     6,000
 
16      P.   Lunalilo school, Oahu
 
17           Design and construction to install an air conditioning
 
18           unit for the second floor computer room.
 
19           Design                                          $ 3,000
 
20           Construction                                     17,000
 
21           Total funding                                    20,000
 

 
 
 
 
 
Page 6                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1      Q.   Lunalilo school, Oahu
 
 2           Design and construction to create a learning
 
 3           environment in the open area between the cafeteria and
 
 4           library.
 
 5           Design                                          $ 2,250
 
 6           Construction                                     12,750
 
 7           Total funding                                    15,000
 
 8      R.   Lunalilo school, Oahu
 
 9           Design and construction to build a library partition
 
10           below student and faculty areas.
 
11           Design                                          $ 2,700
 
12           Construction                                     15,300
 
13           Total funding                                    18,000
 
14      S.   Lunalilo school, Oahu
 
15           Design and construction to install an automatic
 
16           electrical sprinkler system.
 
17           Design                                          $ 3,000
 
18           Construction                                     17,000
 
19           Total funding                                    20,000
 

 
 
 
 
 
 
 
 
 
Page 7                                                     
                                     H.B. NO.1584       
                                                        
                                                        

 
 1      T.   Young street, Oahu
 
 2           Plans, land acquisition, design, and construction to
 
 3           build an L-shaped park along Young street between south
 
 4           Beretania street and south King street, and Keeaumoku
 
 5           street and Kaheka street, to include an open air
 
 6           amphitheater, pond, soccer field, child play areas, and
 
 7           swimming pool.
 
 8           Plans                                             5,000
 
 9           Land                                        $15,000,000
 
10           Design                                        1,495,000
 
11           Construction                                  5,000,000
 
12           Total funding                                21,500,000
 
13      SECTION 2.  The sums appropriated for the respective capital
 
14 improvement projects set forth in section 1 shall be expended by
 
15 the department of accounting and general services for the
 
16 purposes of this Act.
 
17      SECTION 3.  This Act shall take effect on July 1, 1999.
 
18 
 
19                           INTRODUCED BY:  _______________________