REPORT TITLE:
24th rep district CIP


DESCRIPTION:
Appropriates funds for capital improvement projects for the
benefit of the twenty-fourth representative district.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                                                        
HOUSE OF REPRESENTATIVES                H.B. NO.1272       
TWENTIETH LEGISLATURE, 1999                                
STATE OF HAWAII                                            
                                                             
________________________________________________________________
________________________________________________________________


                   A  BILL  FOR  AN  ACT

RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE
   TWENTY-FOURTH REPRESENTATIVE DISTRICT.


BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 1      SECTION 1.  The following sums, or so much thereof as shall
 
 2 be sufficient to finance the projects listed in this Act, are
 
 3 hereby appropriated out of the general revenues of the State of
 
 4 Hawaii for fiscal year 1999-2000.
 
 5 1.   To be expended by the department of accounting and general
 
 6 services:
 
 7      A.   Lincoln school, Oahu
 
 8           Equipment to install a motion alarm system and for
 
 9           maintenance costs for classrooms.
 
10           Equipment                                      $ 30,000
 
11           Total funding                                    30,000
 
12      B.   Lincoln school, Oahu
 
13           Equipment to install security screens in every
 
14           classroom.
 
15           Equipment                                      $210,000
 
16           Total funding                                   210,000
 
17      C.   Lincoln school, Oahu
 
18           Design, construction, and equipment to repair the
 
19           structural metal beams and to prep and paint the roof
 
20           deck.
 

 
Page 2                                                     
                                     H.B. NO.1272       
                                                        
                                                        

 
 1           Design                                         $  1,000
 
 2           Construction                                    248,000
 
 3           Equipment                                         1,000
 
 4           Total funding                                   250,000
 
 5      D.   Lincoln school, Oahu
 
 6           Equipment to provide safe playground surfacing material
 
 7           and frames for the existing play apparatus.
 
 8           Equipment                                       $23,000
 
 9           Total funding                                    23,000
 
10      E.   Lincoln school, Oahu
 
11           Design, construction, and equipment to build connecting
 
12           concrete sidewalks at the ewa end of buildings B and D.
 
13           Design                                          $ 1,000
 
14           Construction                                     10,000
 
15           Equipment                                         1,000
 
16           Total funding                                    12,000
 
17      F.   Lincoln school, Oahu
 
18           Design, construction, and equipment to resurface the
 
19           parking lot.
 
20           Design                                         $  1,000
 
21           Construction                                    123,000
 
22           Equipment                                         1,000
 
23           Total funding                                   125,000
 

 
Page 3                                                     
                                     H.B. NO.1272       
                                                        
                                                        

 
 1      G.   Roosevelt high school, Oahu
 
 2           Plans and design for a multipurpose
 
 3           educational/athletic facility, including an
 
 4           environmental assessment and an environmental hazard
 
 5           abatement plan.
 
 6           Plans                                          $  1,000
 
 7           Design                                          903,000
 
 8           Total funding                                   904,000
 
 9      H.   Roosevelt high school, Oahu
 
10           Plans and design for an air conditioning system in
 
11           building A.
 
12           Plans                                           $ 1,000
 
13           Design                                           49,000
 
14           Total funding                                    50,000
 
15      I.   Stevenson middle school, Oahu
 
16           Equipment for security screens.
 
17           Equipment                                       $50,000
 
18           Total funding                                    50,000
 
19      J.   Stevenson middle school, Oahu
 
20           Design, construction, and equipment to install rails.
 

 
 
 
 
 
 
 
Page 4                                                     
                                     H.B. NO.1272       
                                                        
                                                        

 
 1           Design                                          $ 1,000
 
 2           Construction                                     48,000
 
 3           Equipment                                         1,000
 
 4           Total funding                                    50,000
 
 5      K.   Stevenson middle school, Oahu
 
 6           Design, construction, and equipment for security gates
 
 7           to the second floor.
 
 8           Design                                         $  1,000
 
 9           Construction                                     98,000
 
10           Equipment                                         1,000
 
11           Total funding                                   100,000
 
12 2.   To be expended by the city and county of Honolulu:
 
13      L.   Makiki park, Oahu
 
14           Design, construction, and equipment to install a new
 
15           air conditioning system and paint the park building.
 
16           Design                                          $ 5,000
 
17           Construction                                     44,000
 
18           Equipment                                         1,000
 
19           Total funding                                    50,000
 
20      SECTION 2.  The sums appropriated for the respective capital
 
21 projects set forth in section 1 shall be expended by the
 
22 designated expending agency for the purposes of this Act.
 

 
 
 
Page 5                                                     
                                     H.B. NO.1272       
                                                        
                                                        

 
 1      SECTION 3.  This Act shall take effect on July 1, 1999.
 
 2 
 
 3                           INTRODUCED BY:  _______________________