SR 63 SD 1

REQUESTING THE PUBLIC UTILITIES COMMISSION, UPON RECEIPT OF HAWAIIAN ELECTRIC COMPANY'S APPLICATION FOR APPROVAL OF THE PROPOSED KAMOKU-PUKELE 138,000 VOLT TRANSMISSION LINE PROJECT IN HONOLULU, TO BIFURCATE THE DOCKET IN ORDER TO FIRST CONSIDER THE ISSUE OF NEED (AMENDED TITLE)

By Senator(s) IHARA / FUKUNAGA / TANIGUCHI / HANABUSA

Report Title: Kamoku-Pukele KV Lines

Description:

 3-17-99        S Offered                                                  
 3-18-99        S Referred to 1. CPN 2. WAM                                
 3-25-99        S Resolution scheduled to be heard by CPN on 04-01-99         
                  at 9:00 a.m. in conference room 016.
 4- 1-99        S The committee on CPN recommends that the measure be         
                  PASSED, WITH AMENDMENTS.
 4- 1-99        S The votes in CPN were as follows: 5 Ayes: Senator(s)        
                  Kanno, Taniguchi, Ihara, Inouye, Slom; Ayes with
                  reservations: Senator(s) ; none Noes: Senator(s) ;
                  and 3 Excused: Senator(s) Bunda, Hanabusa, Matsuura
 4- 5-99        S Reported from CPN (Stand Com. Rep. No. 1354) as
                  amended  (SD 1), with recommendation of referral to         
                  WAM
 4- 5-99        S Report adopted, as amended (SD 1) and referred to
                  WAM