HRS 0269-0027_0005 ANNOTATIONS

Case Notes

Where general public had substantial opportunity to provide input, public utilities commission had established necessary procedures by which ratepayers could manifest their consent in order to persuade commission that cost of underground routing of transmission lines was acceptable. 81 H. 459, 918 P.2d 561.

 

Previous Next